Armoured or reinforced safes, strong-boxes and doors and safe deposit lockers for strong-rooms, cash or deed boxes and the like, of base metal

Armoured or reinforced safes, strong-boxes and doors and safe deposit lockers for strong-rooms, cash or deed boxes and the like, of base metal: This PCR applies to…

Lifecycle status
Candidate
Content maturity
Authored methodology
Current version
No published version
Readiness
Review required
Last updated

Methodology and translation states come from the source record; publishing this website does not change their review status.

Content languages

zh-CN · Aligned
Status, classification and source details

Readiness

  • Warnings methodology_not_reviewed Authored methodology is candidate guidance and still requires methodology review.

Classification mapping

CPC 3.0:42993 · exact

Source

1. Scope and Applicability

This PCR applies to factory-gate production of finished base-metal armoured or reinforced safes, strong-boxes, strong-room doors, safe-deposit lockers, cash boxes, deed boxes, and functionally similar secure-storage products within CPC 3.0 code 42993. It covers product configurations whose protective body or door is fabricated from base metal and reinforced by a security-barrier construction.

The PCR does not cover ordinary non-reinforced cabinets, furniture, locks supplied as stand-alone products, alarm systems, vault construction performed at the customer site, or upstream production of steel, coatings, barrier constituents, electronics, packaging, and purchased components. A data package shall identify whether it represents a complete safe, strong-box, strong-room door, locker bank, or smaller cash or deed box; products with materially different constructions or declared protection grades shall not be averaged without a documented representativeness justification.

2. Product Category Identity

FieldValue
canonical_pcr_idpcr.metal-products-machinery-and-equipment.fabricated-metal-products-except-machinery-and-equipment.armoured-or-reinforced-safes-strong-boxes-and-doors-and-safe-deposit-lockers-for-strong-f62c9b83
classification_refsCPC 3.0: 42993
covered_productsFinished base-metal armoured or reinforced safes, strong-boxes, strong-room doors, safe-deposit lockers, cash boxes, deed boxes, and like secure-storage products
excluded_productsOrdinary non-reinforced cabinets; stand-alone locks and alarms; on-site strong-room construction; upstream materials and purchased components
representative_productOne declared finished secure-storage product whose base-metal body or door and reinforcing barrier satisfy the producer's stated protection specification
production_routeSheet-metal cutting and forming, body and door welding, barrier and lock assembly, applicable surface finishing, packaging, and factory release
market_stateFinished product at the manufacturing-site gate, excluding external transport packaging from the net product mass

3. Reference Flow

FieldValue
WhatProvision of a finished armoured or reinforced secure-storage product at the manufacturing-site gate
How much1000 kg net finished product, excluding external transport packaging
How wellThe declared product type, security or fire-performance designation where applicable, lock configuration, principal barrier construction, and factory acceptance status are stated
How long or cycleOne manufactured and released product; service life is disclosed separately and is not embedded in the reference amount
reference_flow_linkfinished_secure_storage_product
FieldValue
Reference amount1000 kg
Reference product flowArmoured or reinforced safes, strong-boxes and doors and safe deposit lockers for strong-rooms, cash or deed boxes and the like, of base metal 35affc80-58a8-406b-9e08-574796726703
Reference flow propertyMass (93a60a56-a3c8-11da-a746-0800200b9a66)
Reference unit groupUnits of mass (93a60a57-a4c8-11da-a746-0800200c9a66)
Reference unitkg
Required qualifiersproduct type; model or product family; security or fire-performance designation where applicable; lock configuration; principal barrier construction; manufacturing geography; data period; net product mass basis; packaging exclusion; factory-gate boundary

When constructing a foreground data package, the items listed in Required qualifiers must be declared in dataset metadata, process notes, reference flow comment, product description, or an equivalent data package field. Missing required qualifiers make the reference flow definition incomplete for that data package.

4. Measurement and Unit Rules

rule_idApplies toRequired propertyRequired unitRule
mr_reference_product_massfinished_secure_storage_productMass (93a60a56-a3c8-11da-a746-0800200b9a66)kgDetermine calibrated net finished-product mass after final assembly and before external transport packaging; normalize the released product total to 1000 kg.
mr_material_and_waste_massall material inputs and solid or liquid waste outputsMass (93a60a56-a3c8-11da-a746-0800200b9a66)kgUse receiving, batch, issue, return, and waste records reconciled to stock change; report wet or dry basis and composition when it changes interpretation.
mr_electricitypurchased and on-site electricityNet calorific value (93a60a56-a3c8-11da-a746-0800200b9a66)MJRecord metered delivered electricity by process; if the meter reports kWh, retain the original reading and convert with 1 kWh = 3.6 MJ.
mr_process_waterprocess_waterMass (93a60a56-a3c8-11da-a746-0800200b9a66)kgUse a mass reading or convert a metered volume with documented density and temperature assumptions; do not merge process water with wastewater.
mr_particulatewelding_particulateMass (93a60a56-a3c8-11da-a746-0800200b9a66)kgPrefer source testing or capture-system mass balance; where an emission factor is necessary, match the actual welding process and consumable and disclose the factor source and controls.

5. System Boundary

rule_idapplies_torulesource_ids
sb_startforeground systemThe boundary starts with purchased materials, components, energy, water, and packaging delivered to the manufacturing site and includes their linked upstream datasets.epd-international-godrej-high-security-safes-2025
sb_manufactureforeground systemInclude sheet-metal preparation and forming, body and door welding, barrier filling or installation, lock and hardware assembly, surface pretreatment and coating when used, curing, packaging, final inspection, rework, and factory release.epd-international-godrej-high-security-safes-2025; us-epa-ap42-electric-arc-welding-1995
sb_exchangesall included processesInclude all known material, component, water, energy, packaging, waste, and direct elementary exchanges; no blanket percentage cut-off is permitted. Any unavailable exchange shall be identified and its omission justified.epd-international-godrej-high-security-safes-2025
sb_wastegenerated wastesInclude on-site handling and treatment preparation and link each waste output to the downstream treatment or recycling scenario selected by the study; do not credit avoided production inside the foreground without an explicitly declared modelling rule.epd-international-godrej-high-security-safes-2025
sb_exclusionsforeground systemExclude capital equipment, factory buildings, employee travel, and downstream distribution, installation, use, maintenance, and end of life unless the study goal explicitly adds them as separately disclosed processes.epd-international-godrej-high-security-safes-2025

Boundary Abstraction

FieldValue
declared_starting_conditionPurchased materials, components, utilities, and packaging as received at the manufacturing site
starting_condition_roleforeground_start
product_classification_scopeCPC 3.0 code 42993 complete finished secure-storage products
recursive_input_ruleA purchased semi-finished safe body, door, locker module, or other same-category product shall be modelled as a separate upstream product input and shall not be silently substituted for its constituent materials.
upstream_dataset_requirementEach purchased input requires a geographically and technologically representative upstream dataset or an explicitly justified proxy.
disclosureDisclose product type, protection designation, manufacturing geography, data period, route coverage, purchased subassemblies, allocation, exclusions, and downstream waste scenarios.

6. Process Inventory Structure

Process Map

process_idprocess_nameinclusioninclusion_conditionrolequantitative_reference
body_fabrication_and_weldingBody fabrication and weldingrequiredInclude cutting, forming, fitting, welding, and associated scrap and direct fume for every product.Converts steel stock into the principal body and door shell.fabricated body and door mass transferred to assembly
barrier_and_lock_assemblyBarrier and lock assemblyrequiredInclude the actual reinforcement, barrier filling or installation, lock fitting, hardware integration, and assembly energy.Produces the complete protective assembly.assembled secure-storage product mass transferred to finishing or release
surface_finishingSurface finishingconditionalInclude when aqueous pretreatment, powder coating, another coating, or curing occurs at the reporting site; record unused route rows as zero or not applicable.Provides the declared surface protection and appearance.surface-finished product mass
packaging_and_final_releasePackaging and final releaserequiredInclude actual factory packaging, final inspection, accepted output, and documented rework before shipment.Releases the reference product at the factory gate.finished_secure_storage_product

Process: Body fabrication and welding (body_fabrication_and_welding)

Inputs

Product flows
Uncoated carbon-steel sheet (steel_sheet)

Specific sheet stock crosses the site boundary for cutting, forming, and welding into the body and door. Determine consumption from issued mass less traceable returns, reconciled with stock change.

  • Selected flow: Uncoated carbon-steel sheet
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure net sheet consumption and normalize with calc_mass_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_body_materials
  • Sources: epd-international-godrej-high-security-safes-2025
Solid welding wire (solid_welding_wire)

Solid consumable electrode crosses the process boundary only when gas metal arc welding or another documented solid-wire route is used. Determine net wire consumption from spool issues, returns, and stock change.

  • Selected flow: Solid welding wire
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Record measured consumption for the applicable welding route; otherwise record zero or not applicable.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Route-specific (route_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_body_materials
  • Sources: us-epa-ap42-electric-arc-welding-1995
Flux-cored wire (flux_cored_wire)

Flux-cored consumable wire crosses the process boundary when the FCAW route is used. Determine net wire consumption from spool issues, returns, and stock change.

  • Selected flow: Flux Cored Wire 1b74a576-06e0-4764-97ce-11a73f8a4752
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Record measured consumption for FCAW; otherwise record zero or not applicable.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Route-specific (route_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_body_materials
  • Sources: us-epa-ap42-electric-arc-welding-1995
Fabrication electricity (electricity_fabrication)

Electricity crosses the process boundary to operate cutting, forming, extraction, and welding equipment. Use submetered energy or a documented machine-load allocation when a dedicated meter is unavailable.

  • Selected flow: Electricity 890a70b7-b677-4e2a-8a1b-7d017e0a10ae
  • Flow property / unit: Net calorific value (93a60a56-a3c8-11da-a746-0800200b9a66); Units of energy (93a60a57-a3c8-11da-a746-0800200c9a66); MJ
  • Amount rule: Record delivered electricity and normalize with calc_energy_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_fabrication_electricity
  • Sources: epd-international-godrej-high-security-safes-2025
Waste flows
Elementary flows

Outputs

Product flows
Waste flows
Steel scrap (steel_scrap)

Offcuts and rejected steel parts leave fabrication as a separately measured waste flow. Record gross collected scrap less any verified internal remelt or direct reuse that never leaves the same process system.

  • Selected flow: Scrap steel c3fc5605-baa3-4b25-9934-ecf7fcbc72da
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure dispatched scrap by scale ticket and normalize with calc_mass_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_fabrication_waste
  • Sources: epd-international-godrej-high-security-safes-2025
Elementary flows
Welding particulate (welding_particulate)

Airborne particulate generated by welding crosses the process boundary after accounting for capture and exhaust controls. Keep the audited particle-size-unspecified identity unless measurement establishes a different exact elementary-flow identity.

  • Selected flow: Particulate matter, particle size unspecified 0ce3dedb-caca-407b-a856-a90470eb8ec0
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Use measured released mass or a documented process- and consumable-specific calculation under calc_welding_particulate.
  • Value mode: Calculated value (calculated_value)
  • Specificity: Route-specific (route_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol ID: cp_welding_emissions
  • Sources: us-epa-ap42-electric-arc-welding-1995

Process: Barrier and lock assembly (barrier_and_lock_assembly)

Inputs

Product flows
Cementitious security-barrier compound (cementitious_barrier)

The formulated cementitious compound crosses the assembly boundary for filling or installing the reinforcing barrier. Measure the complete supplied mixture as one product exchange and disclose its formulation basis without splitting it into unverified constituents.

  • Selected flow: Cementitious security-barrier compound
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Reconcile batch input, returned material, and residual waste, then normalize with calc_mass_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_assembly_materials
  • Sources: epd-international-godrej-high-security-safes-2025
Lock assembly (lock_assembly)

The complete declared lock assembly crosses the site boundary for installation in the door or box. Record the purchased assembly mass and disclose mechanical, electronic, or combined configuration.

  • Selected flow: Secure-storage lock assembly
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Sum accepted lock assemblies installed in released products and normalize their mass with calc_mass_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_assembly_materials
  • Sources: epd-international-godrej-high-security-safes-2025
Assembly electricity (electricity_assembly)

Electricity crosses the process boundary for mixing, filling, curing support, fitting, and lock or hardware assembly. Use a dedicated meter or a documented equipment-time allocation.

  • Selected flow: Electricity 890a70b7-b677-4e2a-8a1b-7d017e0a10ae
  • Flow property / unit: Net calorific value (93a60a56-a3c8-11da-a746-0800200b9a66); Units of energy (93a60a57-a3c8-11da-a746-0800200c9a66); MJ
  • Amount rule: Record delivered electricity and normalize with calc_energy_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_assembly_electricity
  • Sources: epd-international-godrej-high-security-safes-2025
Waste flows
Elementary flows

Outputs

Product flows
Waste flows
Barrier-compound waste (barrier_compound_waste)

Off-spec, spilled, or residual cementitious barrier compound leaves assembly as a separately quantified waste. Report wet or cured state and the downstream treatment route.

  • Selected flow: Cementitious security-barrier compound waste
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure collected waste by batch or container mass and normalize with calc_mass_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_assembly_waste
  • Sources: epd-international-godrej-high-security-safes-2025
Elementary flows

Process: Surface finishing (surface_finishing)

Inputs

Product flows
Powder coating (powder_coating)

Powder coating crosses the process boundary when the product uses an on-site powder-coating route. Determine net consumption from issued powder, recoverable recirculation, stock change, and separately collected waste.

  • Selected flow: Powder Coating 0c581697-0eed-4b86-a070-b94966eb7344
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Record net fresh powder consumed; otherwise record zero or not applicable for a non-powder route.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Route-specific (route_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_finishing_materials
  • Sources: epd-international-godrej-high-security-safes-2025
Process water (process_water)

Process water crosses the boundary when aqueous cleaning or pretreatment is performed on site. Record make-up water separately from recirculated internal water.

  • Selected flow: Process Water 94a04f7e-2d5c-41f0-b182-d54a3b373a02
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Record net make-up water for the applicable route; otherwise record zero or not applicable.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_finishing_utilities
  • Sources: epd-international-godrej-high-security-safes-2025
Finishing electricity (electricity_finishing)

Electricity crosses the process boundary for pretreatment equipment, booths, extraction, recovery, and curing. Submeter the route or allocate a shared meter by documented equipment operating time and load.

  • Selected flow: Electricity 890a70b7-b677-4e2a-8a1b-7d017e0a10ae
  • Flow property / unit: Net calorific value (93a60a56-a3c8-11da-a746-0800200b9a66); Units of energy (93a60a57-a3c8-11da-a746-0800200c9a66); MJ
  • Amount rule: Record delivered electricity for the applicable finishing route and normalize with calc_energy_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Route-specific (route_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_finishing_utilities
  • Sources: epd-international-godrej-high-security-safes-2025
Waste flows
Elementary flows

Outputs

Product flows
Waste flows
Powder-coating waste (powder_coating_waste)

Spent or unrecoverable coating powder leaves finishing as a discrete waste flow. Exclude internally recovered powder that remains within the same process loop.

  • Selected flow: Powder coating waste 9aa53a82-5462-400e-9096-efab7718201f
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure dispatched or treated waste mass and normalize with calc_mass_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Route-specific (route_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_finishing_wastes
  • Sources: epd-international-godrej-high-security-safes-2025
Surface-treatment wastewater (surface_treatment_wastewater)

Wastewater discharged from aqueous cleaning or pretreatment leaves finishing as a distinct liquid waste flow. Record discharge mass and disclose whether on-site treatment occurs before the measured boundary point.

  • Selected flow: Aqueous surface-treatment wastewater
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure discharged wastewater for the applicable route and normalize with calc_mass_normalization; otherwise record zero or not applicable.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Route-specific (route_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_finishing_wastes
  • Sources: epd-international-godrej-high-security-safes-2025
Elementary flows

Process: Packaging and final release (packaging_and_final_release)

Inputs

Product flows
Corrugated cardboard (corrugated_cardboard)

Corrugated cardboard crosses the process boundary as product-specific transport packaging. Determine the mass installed on released products, excluding returned or unused stock.

  • Selected flow: Corrugated cardboard 8bde297e-98df-463f-bcb4-0db52bf6e0b5
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure packaging mass and normalize with calc_mass_normalization.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_packaging_materials
  • Sources: epd-international-godrej-high-security-safes-2025
Pine-wood pallet (pine_pallet)

A pine-wood pallet crosses the process boundary when it is shipped with the product. Record the dry or as-received pallet mass and any reuse assumption separately.

  • Selected flow: Pine-wood pallet
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure pallet mass shipped with released products and normalize with calc_mass_normalization; otherwise record zero or not applicable.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_packaging_materials
  • Sources: epd-international-godrej-high-security-safes-2025
Plastic film (plastic_film)

Plastic film crosses the process boundary as wrapping or protective packaging when used. Determine installed film mass from issue and product-pack records.

  • Selected flow: Plastic Film 8c3dd40c-a22b-48b5-bdec-7da4d3282bfa
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Measure film mass shipped with released products and normalize with calc_mass_normalization; otherwise record zero or not applicable.
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: 1000 kg finished secure-storage product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol ID: cp_packaging_materials
  • Sources: epd-international-godrej-high-security-safes-2025
Waste flows
Elementary flows

Outputs

Product flows
Finished secure-storage product (finished_secure_storage_product)

The accepted complete safe, strong-box, strong-room door, locker, cash box, deed box, or like product leaves final release as the quantitative reference. Record net finished mass before external transport packaging.

  • Selected flow: Armoured or reinforced safes, strong-boxes and doors and safe deposit lockers for strong-rooms, cash or deed boxes and the like, of base metal 35affc80-58a8-406b-9e08-574796726703
  • Flow property / unit: Mass (93a60a56-a3c8-11da-a746-0800200b9a66); Units of mass (93a60a57-a4c8-11da-a746-0800200c9a66); kg
  • Amount rule: Set the normalized output to exactly 1000 kg after reconciling measured accepted production.
  • Value mode: Fixed value (fixed_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: Reference product output
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Identity reference (identity_reference)
  • Collection protocol ID: cp_finished_product
  • Sources: unsd-cpc-3-0-structure-2025; epd-international-godrej-high-security-safes-2025
Waste flows
Elementary flows

7. Allocation and Co-product Handling

rule_idapplies_torulesource_ids
al_avoidall shared processesAvoid allocation through process subdivision, dedicated meters, batch records, and direct assignment to the declared product family wherever practicable.
al_mass_balancesteel, barrier compound, coating, water, and packagingReconcile inputs, accepted product, internal returns, stock change, and measured waste before allocation; internal recycling shall not be counted as both a fresh input reduction and a credited output.
al_shared_energyshared electricityAllocate only the residual shared amount using a causal physical driver such as measured machine operating time multiplied by rated or measured load; document the driver and sensitivity.
al_multi_productunavoidable multi-product productionIf subdivision and causal assignment are infeasible, use mass allocation only when mass demonstrably represents resource use; otherwise select and justify another physical relationship and report an unallocated sensitivity case.epd-international-godrej-high-security-safes-2025
al_scraprecyclable steel scrap and other wastesReport the waste at the factory boundary and connect the chosen downstream treatment dataset; do not apply an avoided-production credit inside the foreground unless required by the declared study method and shown separately.epd-international-godrej-high-security-safes-2025

8. Foreground Data Collection, Calculation, and Quality Rules

Data Collection Protocols

protocol_idprocess_idflow_rolerecord_typeraw_fieldscollection_methodunitfrequencytemporal_coveragesite_scopeaggregation_rulequality_evidence
cp_body_materialsbody_fabrication_and_weldingsteel sheet and route-specific welding wire inputsreceiving and stock recorditem identity; lot; opening stock; receipts; issues; returns; closing stock; massreconcile enterprise records to physical stockkgeach lot and monthly closeat least 12 consecutive representative monthsall fabrication lines serving the declared productsum net consumption by exact material identity and welding routepurchase records; calibrated scales; stock reconciliation
cp_fabrication_electricitybody_fabrication_and_weldingelectricity_fabricationmeter and equipment logmeter start; meter end; equipment; operating time; load; lossesdedicated submeter or documented load-time allocationkWh and MJcontinuous or each shiftsame representative period as productionall included fabrication equipmentsum delivered energy and convert retained kWh readings to MJmeter calibration; allocation worksheet
cp_fabrication_wastebody_fabrication_and_weldingsteel_scrapwaste dispatch recordwaste identity; container tare; gross mass; destination; datecalibrated scale and dispatch ticketkgeach dispatchsame representative period as productionfabrication waste collection pointssum net dispatched mass by destinationscale calibration; tickets; recycler receipt
cp_welding_emissionsbody_fabrication_and_weldingwelding_particulateemission test or operating recordprocess; consumable; mass consumed; capture efficiency; exhaust measurement; factor referencesource test or process-specific calculationkgeach test and monthly activityrepresentative operating conditions and annualized data periodevery welding route in scopecalculate released mass after documented controls and sum by routetest report; factor edition; control inspection
cp_assembly_materialsbarrier_and_lock_assemblycementitious_barrier and lock_assemblybatch and component issue recordidentity; formulation or model; batch; receipts; issues; returns; stock change; massbatch reconciliation and installed-component count or masskgeach batch or production orderat least 12 consecutive representative monthsall assembly lines serving the declared productsum net installed or consumed mass by exact componentbatch sheet; bill of materials; scale records
cp_assembly_electricitybarrier_and_lock_assemblyelectricity_assemblymeter and equipment logmeter readings; equipment; operating time; loadsubmeter or documented load-time allocationkWh and MJcontinuous or each shiftsame representative period as productionall included assembly equipmentsum delivered energy by product familymeter calibration; allocation worksheet
cp_assembly_wastebarrier_and_lock_assemblybarrier_compound_wastebatch residual and waste recordstate; batch; container tare; gross mass; destinationbatch reconciliation and calibrated weighingkgeach batch or dispatchsame representative period as productionall barrier preparation and filling pointssum net waste mass by state and destinationscale record; waste manifest
cp_finishing_materialssurface_finishingpowder_coatingcoating issue and recovery recordcoating identity; batch; fresh issue; recovered return; stock change; wastebooth-level material balancekgeach batch and monthly closesame representative period as productioneach finishing route usedfresh issue plus opening stock minus return and closing stockbatch sheet; inventory record; scale calibration
cp_finishing_utilitiessurface_finishingprocess_water and electricity_finishingutility metermeter start; meter end; route; operating time; density assumption if neededdedicated meter or documented route allocationkg; kWh; MJcontinuous or each shiftsame representative period as productionall included pretreatment, booth, recovery, and curing equipmentsum by route and convert units under Section 4meter calibration; allocation and conversion worksheet
cp_finishing_wastessurface_finishingpowder_coating_waste and surface_treatment_wastewaterwaste and discharge recordidentity; state; volume or mass; density; treatment point; destinationcalibrated weighing or flow metering at the declared boundarykgeach dispatch or continuous dischargesame representative period as productionevery included finishing routesum separately by exact waste identity and treatment routewaste manifest; meter calibration; treatment log
cp_packaging_materialspackaging_and_final_releasecorrugated cardboard, pine pallet, and plastic filmpackaging issue and pack recordmaterial identity; supplier; units; unit mass; issues; returns; shipped quantityweigh representative items and reconcile issues to released productskgeach packaging design and monthly closesame representative period as productionall packaging stations for the declared productsum installed mass separately for each packaging materialpack specification; scale records; stock reconciliation
cp_finished_productpackaging_and_final_releasefinished_secure_storage_productfinal inspection and production recordproduct type; model; protection designation; lock configuration; accepted count; net mass; rejected countcalibrated weighing and acceptance recordkgeach product or statistically justified homogeneous batchsame representative period as all inputsall release points for the declared productsum accepted net mass before packaging; normalize to 1000 kgscale calibration; inspection release; production ledger

Calculation Rules

rule_idApplies toFormula or ruleInputsOutputsource_ids
calc_mass_normalizationmaterial inputs and mass outputsnormalized amount = period exchange mass / period accepted net product mass × 1000 kgexchange mass; accepted net product masskg per 1000 kg finished product
calc_energy_normalizationelectricity inputsconvert retained kWh reading to MJ with 3.6 MJ per kWh, then normalized energy = period MJ / period accepted net product mass × 1000 kgmeter reading; accepted net product massMJ per 1000 kg finished product
calc_welding_particulatewelding_particulatereleased particulate = measured exhaust mass, or consumable/activity amount × matched particulate factor × (1 − verified capture fraction); do not use a factor for a different welding process or electrodesource test or activity; matched factor; control performancekg particulate per 1000 kg finished productus-epa-ap42-electric-arc-welding-1995
calc_mass_balancesteel, barrier compound, coating, water, and packaginginput + opening stock = product incorporation + output waste + internal return + closing stock + documented discrepancy; investigate material discrepancies before normalizationinput; stock; incorporated mass; returns; wastesreconciled mass balance and discrepancy

Data Quality Requirements

requirement_idApplies toRequirementEvidence
dqr_identityevery exchangePreserve exact material, component, waste, and elementary-flow identity; do not aggregate atomic rows into utilities, energy carriers, materials, residues, or emissions groups.purchase specification; process record; waste code; flow audit
dqr_timeforeground dataUse at least 12 consecutive representative months or justify a shorter campaign for non-continuous production and disclose seasonality, start-up, and abnormal-operation treatment.dated raw records; production calendar; exclusion log
dqr_geographyupstream dataMatch the manufacturing and supply geography and disclose any geographic proxy.supplier location; dataset geography; proxy justification
dqr_technologyprocesses and upstream dataMatch the actual steel form, welding process and consumable, barrier formulation, lock type, finishing route, controls, and packaging design.bill of materials; routing; equipment and control records
dqr_completenessforeground inventoryReconcile all listed rows, report route-inapplicable rows as zero or not applicable, and document every omitted known exchange; absence of an exact UUID does not permit omission.signed inventory checklist; mass and energy balances; omission register
dqr_uncertaintymeasured and calculated valuesRecord meter or scale uncertainty, sampling coverage, allocation uncertainty, conversion assumptions, and emission-factor uncertainty where used.calibration certificates; sampling plan; calculation workbook
dqr_consistencybilingual and structured recordsKeep English and Chinese row ids, UUIDs, process ids, units, route conditions, and rules aligned with the generated structured projection.bilingual comparison; clean second sync; schema validation

9. Validation Rules

rule_idapplies_torulesource_ids
val_referencereference flowConfirm exactly one quantitative-reference output named finished_secure_storage_product, equal to 1000 kg net finished product, with the audited product UUID and mass references.unsd-cpc-3-0-structure-2025
val_identityproduct categoryConfirm CPC 3.0 code 42993 and the declared product type are within the covered boundary and that exclusions are not represented as the reference product.unsd-cpc-3-0-structure-2025
val_inventoryprocess inventoryConfirm all 19 atomic inventory rows are present exactly once, each has one direction and flow type, and every UUID-empty row is listed in manifest unresolved review metadata.
val_routesconditional processes and rowsConfirm route applicability is declared and every inapplicable welding, finishing, water, wastewater, coating, or packaging row is explicitly zero or not applicable rather than omitted.us-epa-ap42-electric-arc-welding-1995; epd-international-godrej-high-security-safes-2025
val_balancemass and energy recordsConfirm the finished-product denominator, material balances, waste destinations, retained electricity readings, unit conversions, and shared-meter allocation worksheets reconcile for the same reporting period.
val_weldingwelding particulateConfirm the particulate calculation matches the documented welding process, consumable, control performance, and audited particle-size-unspecified flow identity.us-epa-ap42-electric-arc-welding-1995
val_sourcesevidenceConfirm every cited source is an original verified document and that no numeric external range is asserted from the single product-specific EPD.epd-international-godrej-high-security-safes-2025; us-epa-ap42-electric-arc-welding-1995
val_projectionbilingual structured packageConfirm English and Chinese semantic alignment, exact Tiangong Chinese base names for UUID-bearing rows, valid manifest and structured schemas, current fingerprints, and a clean second structured sync.

10. Published Dataset Profile

FieldValue
dataset_roleProduct-specific or representative foreground manufacturing data package for CPC 42993 secure-storage products
downstream_useConstruction of process and lifecycle-model datasets with separately selected upstream and downstream scenarios
allowed_useFactory-gate comparison only when product type, performance designation, lock configuration, principal construction, geography, data period, allocation, and completeness are equivalent
excluded_useDirect comparison of unlike safe, door, locker, cash-box, or deed-box configurations; use-phase or end-of-life claims without added scenario modelling; claims that unresolved UUIDs are verified identities
required_metadataproduct type; model family; security or fire designation; lock configuration; principal construction; net mass; geography; technology; data period; route conditions; allocation; exclusions; source and UUID audit references
required_quality_disclosuremeasurement coverage; mass and energy balance; meter and scale uncertainty; upstream proxies; emission-factor use; omitted exchanges; unresolved UUIDs; absence of external quantity ranges
update_triggerChange in product construction, protection designation, lock system, welding route, barrier formulation, coating route, energy supply, packaging design, site geography, allocation, or source evidence

11. Data Sources

source_idtypereferenceused_for
unsd-cpc-3-0-structure-2025official_guidanceUnited Nations Statistics Division, CPC Version 3.0 Structure, 30 June 2025, https://unstats.un.org/unsd/classifications/Econ/Download/In%20Text/CPC_Ver_3.0_Structure_30Jun2025.csvOfficial CPC 42993 product identity and classification boundary
epd-international-godrej-high-security-safes-2025datasetGodrej & Boyce Manufacturing Company Limited, High Security Safes, EPD-IES-0024476, 2025, https://api.prod.environdec.com/api/v1/EPDLibrary/Files/EPDs/d6af31c9-e7e3-48f0-e9e4-08ddacd8e900/DocumentsOriginal product-specific evidence for construction, manufacturing stages, utilities, wastes, packaging, declared mass basis, and factory-gate process decomposition; not used to assert an external quantity range
us-epa-ap42-electric-arc-welding-1995official_guidanceUnited States Environmental Protection Agency, AP-42 Section 12.19 Electric Arc Welding, January 1995, https://www.epa.gov/sites/production/files/2020-11/documents/c12s19.pdfOriginal official evidence for solid-wire and flux-cored welding routes, particulate generation, and route-matched measurement or calculation

Raw downloads

These files are byte-identical to the canonical files for this revision in the repository.

Structured rule index

This index comes from verified structured.yaml and retains the canonical English rule text.

System boundary rules · 5
Rule IDApplies toRuleSource IDs
sb_startforeground systemThe boundary starts with purchased materials, components, energy, water, and packaging delivered to the manufacturing site and includes their linked upstream datasets.epd-international-godrej-high-security-safes-2025
sb_manufactureforeground systemInclude sheet-metal preparation and forming, body and door welding, barrier filling or installation, lock and hardware assembly, surface pretreatment and coating when used, curing, packaging, final inspection, rework, and factory release.epd-international-godrej-high-security-safes-2025, us-epa-ap42-electric-arc-welding-1995
sb_exchangesall included processesInclude all known material, component, water, energy, packaging, waste, and direct elementary exchanges; no blanket percentage cut-off is permitted. Any unavailable exchange shall be identified and its omission justified.epd-international-godrej-high-security-safes-2025
sb_wastegenerated wastesInclude on-site handling and treatment preparation and link each waste output to the downstream treatment or recycling scenario selected by the study; do not credit avoided production inside the foreground without an explicitly declared modelling rule.epd-international-godrej-high-security-safes-2025
sb_exclusionsforeground systemExclude capital equipment, factory buildings, employee travel, and downstream distribution, installation, use, maintenance, and end of life unless the study goal explicitly adds them as separately disclosed processes.epd-international-godrej-high-security-safes-2025
Allocation rules · 5
Rule IDApplies toRuleSource IDs
al_avoidall shared processesAvoid allocation through process subdivision, dedicated meters, batch records, and direct assignment to the declared product family wherever practicable.
al_mass_balancesteel, barrier compound, coating, water, and packagingReconcile inputs, accepted product, internal returns, stock change, and measured waste before allocation; internal recycling shall not be counted as both a fresh input reduction and a credited output.
al_shared_energyshared electricityAllocate only the residual shared amount using a causal physical driver such as measured machine operating time multiplied by rated or measured load; document the driver and sensitivity.
al_multi_productunavoidable multi-product productionIf subdivision and causal assignment are infeasible, use mass allocation only when mass demonstrably represents resource use; otherwise select and justify another physical relationship and report an unallocated sensitivity case.epd-international-godrej-high-security-safes-2025
al_scraprecyclable steel scrap and other wastesReport the waste at the factory boundary and connect the chosen downstream treatment dataset; do not apply an avoided-production credit inside the foreground unless required by the declared study method and shown separately.epd-international-godrej-high-security-safes-2025
Validation rules · 8
Rule IDApplies toRuleSource IDs
val_referencereference flowConfirm exactly one quantitative-reference output named finished_secure_storage_product, equal to 1000 kg net finished product, with the audited product UUID and mass references.unsd-cpc-3-0-structure-2025
val_identityproduct categoryConfirm CPC 3.0 code 42993 and the declared product type are within the covered boundary and that exclusions are not represented as the reference product.unsd-cpc-3-0-structure-2025
val_inventoryprocess inventoryConfirm all 19 atomic inventory rows are present exactly once, each has one direction and flow type, and every UUID-empty row is listed in manifest unresolved review metadata.
val_routesconditional processes and rowsConfirm route applicability is declared and every inapplicable welding, finishing, water, wastewater, coating, or packaging row is explicitly zero or not applicable rather than omitted.us-epa-ap42-electric-arc-welding-1995, epd-international-godrej-high-security-safes-2025
val_balancemass and energy recordsConfirm the finished-product denominator, material balances, waste destinations, retained electricity readings, unit conversions, and shared-meter allocation worksheets reconcile for the same reporting period.
val_weldingwelding particulateConfirm the particulate calculation matches the documented welding process, consumable, control performance, and audited particle-size-unspecified flow identity.us-epa-ap42-electric-arc-welding-1995
val_sourcesevidenceConfirm every cited source is an original verified document and that no numeric external range is asserted from the single product-specific EPD.epd-international-godrej-high-security-safes-2025, us-epa-ap42-electric-arc-welding-1995
val_projectionbilingual structured packageConfirm English and Chinese semantic alignment, exact Tiangong Chinese base names for UUID-bearing rows, valid manifest and structured schemas, current fingerprints, and a clean second structured sync.
Processes and inputs/outputs · 4
Process IDProcess nameInput flowsOutput flows
body_fabrication_and_weldingBody fabrication and welding42
barrier_and_lock_assemblyBarrier and lock assembly31
surface_finishingSurface finishing32
packaging_and_final_releasePackaging and final release31

Complete field inspector

Loads this record’s complete manifest and structured projection on demand; values are never truncated. Requires JavaScript.

On this page

1. Scope and Applicability2. Product Category Identity3. Reference Flow4. Measurement and Unit Rules5. System BoundaryBoundary Abstraction6. Process Inventory StructureProcess MapProcess: Body fabrication and welding (body_fabrication_and_welding)InputsProduct flowsUncoated carbon-steel sheet (steel_sheet)Solid welding wire (solid_welding_wire)Flux-cored wire (flux_cored_wire)Fabrication electricity (electricity_fabrication)Waste flowsElementary flowsOutputsProduct flowsWaste flowsSteel scrap (steel_scrap)Elementary flowsWelding particulate (welding_particulate)Process: Barrier and lock assembly (barrier_and_lock_assembly)InputsProduct flowsCementitious security-barrier compound (cementitious_barrier)Lock assembly (lock_assembly)Assembly electricity (electricity_assembly)Waste flowsElementary flowsOutputsProduct flowsWaste flowsBarrier-compound waste (barrier_compound_waste)Elementary flowsProcess: Surface finishing (surface_finishing)InputsProduct flowsPowder coating (powder_coating)Process water (process_water)Finishing electricity (electricity_finishing)Waste flowsElementary flowsOutputsProduct flowsWaste flowsPowder-coating waste (powder_coating_waste)Surface-treatment wastewater (surface_treatment_wastewater)Elementary flowsProcess: Packaging and final release (packaging_and_final_release)InputsProduct flowsCorrugated cardboard (corrugated_cardboard)Pine-wood pallet (pine_pallet)Plastic film (plastic_film)Waste flowsElementary flowsOutputsProduct flowsFinished secure-storage product (finished_secure_storage_product)Waste flowsElementary flows7. Allocation and Co-product Handling8. Foreground Data Collection, Calculation, and Quality RulesData Collection ProtocolsCalculation RulesData Quality Requirements9. Validation Rules10. Published Dataset Profile11. Data Sources