TianGong PCR产品类别规则

Portable electric lamps, lighting fittings, non-electrical lamps, and illuminated signs

Portable electric lamps, lighting fittings, non-electrical lamps, and illuminated signs: This PCR governs foreground factory-gate data production for complete lighting…

Lifecycle status
Candidate
Content maturity
Authored methodology
Current version
No published version
Readiness
Review required
Last updated

Methodology and translation states come from the source record; publishing this website does not change their review status.

Content languages

zh-CN · Aligned
Status, classification and source details

Readiness

  • Warnings methodology_not_reviewed Authored methodology is candidate guidance and still requires methodology review.

Classification mapping

CPC 3.0:46531 · exact

Source

1. Scope and Applicability

This PCR governs foreground factory-gate data production for complete lighting or illuminated-identification products within the semantic boundary stated below. It covers product-specific material and component receipt, optional on-site surface finishing, assembly, final testing, packing, and release at the manufacturing gate. The product instance must be declared; this PCR does not treat the listed product forms as interchangeable.

Use-stage electricity or fuel, installation, maintenance, distribution after the factory gate, and end-of-life are outside the foreground boundary. Upstream production of purchased materials, components, electricity, fuels, water, and packaging remains connected through supplier or background datasets. Manufacture of separate lamps or light sources, Christmas-tree lighting sets, LED-only luminaires classified separately, public-space or thoroughfare lighting fittings, vehicle or cycle lamps, and separately traded parts are excluded.

The representative route is assembly and factory testing of one finished electric luminaire from purchased mechanical, optical, and electrical components. Surface finishing, a primary battery, a non-electrical fuel reservoir and wick, and an illuminated-sign face panel are conditional elements. This common route avoids enumerating every product-form and material combination.

2. Product Category Identity

FieldValue
canonical_pcr_idpcr.metal-products-machinery-and-equipment.electrical-machinery-and-apparatus.portable-electric-lamps-designed-to-function-by-their-own-source-of-energy-except-those-8a00f87c
classification_refsCPC 3.0: 46531
covered_productsSelf-powered portable electric lamps other than cycle or motor-vehicle lamps; ceiling or wall electric lighting fittings other than fittings for public open spaces or thoroughfares; electric table, desk, bedside, and floor-standing lamps; non-electrical lamps and lighting fittings; illuminated signs, illuminated name-plates, and like finished goods.
excluded_productsCycle and motor-vehicle lamps; public-space or thoroughfare lighting fittings; Christmas-tree lighting sets; luminaires designed solely for LED light sources when classified separately; separately traded lamps/light sources; and separately traded parts.
representative_productOne complete electric indoor luminaire assembled from a mechanical chassis, optical component, wiring, control gear, and declared light-source module, factory-tested and packed for sale.
production_routePurchased-component receipt; conditional chassis surface finishing; mechanical/electrical or fuel-system assembly; performance and safety testing; packing; factory-gate release.
market_stateComplete finished and packed product at the manufacturer's gate, with the light source, control gear, battery, fuel reservoir, wick, mounting hardware, and sign panel included or excluded exactly as sold and declared.

3. Reference Flow

FieldValue
WhatSupply a declared complete finished lighting or illuminated-identification product ready for its intended operation.
How much1 kg of finished product.
How wellConforms to the declared product subtype, outgoing luminous flux or illuminated visual area, rated electrical or fuel-system characteristics, included components, safety/performance test criteria, and packaging state.
How long or cycleOne factory production cycle to the manufacturing gate; assigned service life and replaceable-component assumptions must be declared for any downstream functional comparison.
reference_flow_linkExactly 1 kg of accepted packed finished-product output from final_testing_and_packaging; item count and packaging mass are mandatory qualifiers.
FieldValue
Reference amount1 kg
Reference product flowFinished packaged lighting or illuminated-identification product within this PCR scope
Reference flow propertyMass 93a60a56-a3c8-11da-a746-0800200b9a66
Reference unit groupUnits of mass 93a60a57-a4c8-11da-a746-0800200c9a66
Reference unitkg
Required qualifiersproduct subtype; electric or non-electrical design; mounting or portability form; model and bill-of-material revision; outgoing luminous flux or illuminated visual area; rated power, voltage and frequency where applicable; light-source technology and whether included/replaceable; control-gear inclusion; battery chemistry, capacity and inclusion where applicable; fuel type and reservoir capacity where applicable; assigned service life; product net mass; packed gross mass; production site and period; packaging configuration

When constructing a foreground data package, the items listed in Required qualifiers must be declared in dataset metadata, process notes, reference flow comment, product description, or an equivalent data package field. Missing required qualifiers make the reference flow definition incomplete for that data package.

The mass-based reference amount is a factory-production accounting basis, not a claim of functional equivalence across product subtypes. Comparative lighting studies must normalize products to compatible light output, service life, operating pattern, and delivered function.

4. Measurement and Unit Rules

rule_idApplies toRequired propertyRequired unitRule
mu_reference_massreference productMass 93a60a56-a3c8-11da-a746-0800200b9a66kgNormalize to 1 kg of accepted complete product in the declared sale configuration. Record item count, net product mass, and packed gross mass for each model or production-weighted model group.
mu_mass_bommaterial, component, intermediate, and waste rowsMass 93a60a56-a3c8-11da-a746-0800200b9a66kgConvert piece counts to dry as-supplied mass from verified component weights; preserve measured moisture or coating-solids basis where it changes mass balance.
mu_electricityelectricity rowsNet calorific value 93a60a56-a3c8-11da-a746-0800200b9a66MJPreserve metered electrical energy and convert from kWh using 1 kWh = 3.6 MJ; disclose voltage level, grid geography, and allocation method.
mu_gas_volumenatural-gas rowVolume 93a60a56-a3c8-22da-a746-0800200c9a66m3State the temperature, pressure, wet/dry basis, and supplier conversion used for metered gas volume; do not combine natural gas with other fuels.
mu_water_massprocess-water rowMass 93a60a56-a3c8-11da-a746-0800200b9a66kgConvert a volume meter to mass only with a documented density and the same temporal aggregation as the finishing batch.
mu_internal_transferforeground intermediatesMasskgThe output mass of each internal intermediate must equal the quantity transferred to the next process plus separately recorded loss, inventory change, or rework.

5. System Boundary

Boundary Abstraction

FieldValue
declared_starting_conditionPurchased chassis, optical, electrical, fuel-system, sign-panel, finishing, utility, and packaging inputs are received at the reporting facility in the actual as-supplied state used for the declared product.
starting_condition_roleThe foreground begins at receipt of purchased inputs and covers only transformations, assembly, tests, packing, and losses controlled by the reporting manufacturer.
product_classification_scopeOne declared finished product instance within the semantic scope of this PCR; adjacent CPC lighting products and separately traded parts remain outside.
recursive_input_ruleIf a complete product within this same PCR category is purchased and incorporated, record it once as a distinct product input with an upstream dataset and do not recursively expand its manufacture inside this foreground dataset.
upstream_dataset_requirementEvery purchased material, component, energy carrier, water flow, and packaging item crossing the boundary requires an upstream dataset matching substance or product identity, geography, technology, and delivery state.
disclosureDeclare outsourced versus on-site operations, included components, coating route, test procedures, rejected-product handling, packaging state, cut-offs, data gaps, and any process shared with other products.
rule_idApplies toRulesource_ids
sb_gate_boundaryall foreground processesInclude receipt-to-factory-gate activities controlled by the manufacturer: applicable finishing, assembly, factory tests, packing, rework, rejects, and on-site waste generation. Exclude installation, downstream distribution, use, maintenance, and end-of-life.pep-ecopassport-psr-0014-2023, us-doe-led-lca-part2-2012
sb_component_completenessproduct bill of materialsInclude every component delivered with the product or needed for the declared sale configuration, and state explicitly whether the light source, control gear, battery, mounting parts, fuel reservoir, wick, or sign panel is supplied.pep-ecopassport-psr-0014-2023, us-doe-luminaires-definition
sb_upstream_connectionpurchased inputsModel upstream raw-material, component, energy, water, and packaging production in linked background datasets; do not count those upstream processes again as foreground manufacturing.us-doe-led-lca-part2-2012
sb_variant_conditionconditional routesInstantiate only the rows and processes physically present for the declared product. Mark demonstrably absent conditional rows not_applicable; never substitute another material, battery chemistry, fuel, or component.un-cpc-3-structure-2025

6. Process Inventory Structure

Process Map

process_idprocess_nameinclusioninclusion_conditionrolequantitative_reference
surface_finishingChassis pretreatment and powder coatingconditionalInclude when metal chassis pretreatment or powder coating is performed under the reporting facility's control.foreground finishingkg coated chassis transferred to assembly
product_assemblyMechanical, optical, electrical, fuel-system, or sign assemblyrequiredInclude the actual assembly operations and only the subtype-specific component rows present in the declared product.foreground assemblyaccepted unpacked assemblies
final_testing_and_packagingFinal test, packing, and factory-gate releaserequiredInclude acceptance tests, rework/reject disposition, primary sales packaging, and release for every declared product.foreground testing and packing1 kg accepted packed finished product

Process: Chassis pretreatment and powder coating (surface_finishing)

Inputs

Product flows
Uncoated metal chassis (uncoated_metal_chassis)

Record the one product-specific metal chassis entering on-site pretreatment or coating.

  • Selected flow: Uncoated metal lighting-product chassis
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed or BOM-derived mass entering the finishing line
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finish_materials
  • Sources: pep-ecopassport-psr-0014-2023
Thermoset powder coating (powder_coating_material)

Record the specific powder coating formulation consumed; do not combine it with liquid paint or pretreatment chemicals.

  • Selected flow: Thermoset polyester powder coating
  • Flow property / unit: Mass / kg
  • Amount rule: Opening stock plus receipts minus closing stock and separately recovered powder
  • Value mode: Calculated value (calculated_value)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_finish_materials
  • Sources:
Alkaline pretreatment chemical (finish_sodium_hydroxide)

Include only when sodium hydroxide is actually added to the metal-pretreatment bath.

  • Selected flow: Sodium hydroxide e0abcced-0611-4c24-9290-5a2c5a0c4169
  • Flow property / unit: Mass 93a60a56-a3c8-11da-a746-0800200b9a66 / kg
  • Amount rule: As-supplied sodium hydroxide product mass issued to the finishing line
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finish_materials
  • Sources:
Finishing water (finish_process_water)

Record process water supplied to pretreatment, rinsing, or booth cleaning within this process.

  • Selected flow: Process Water 94a04f7e-2d5c-41f0-b182-d54a3b373a02
  • Flow property / unit: Mass 93a60a56-a3c8-11da-a746-0800200b9a66 / kg
  • Amount rule: Metered or tank-balance water entering the finishing process
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finish_materials
  • Sources:
Finishing electricity (finish_electricity)

Record electricity supplied to pretreatment pumps, ventilation, powder application, and curing equipment.

  • Selected flow: Electricity 890a70b7-b677-4e2a-8a1b-7d017e0a10ae
  • Flow property / unit: Net calorific value 93a60a56-a3c8-11da-a746-0800200b9a66 / MJ
  • Amount rule: Submetered electricity or documented equipment-runtime allocation
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finish_energy
  • Sources:
Curing natural gas (finish_natural_gas)

Include only when gaseous natural gas is burned in an on-site curing oven.

  • Selected flow: natural gas in the gaseous state 4f19ca0e-7b3b-11dd-ad8b-0800200c9a66
  • Flow property / unit: Volume 93a60a56-a3c8-22da-a746-0800200c9a66 / m3
  • Amount rule: Metered gas allocated to the declared finishing batches
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finish_energy
  • Sources:
Waste flows
Elementary flows

Outputs

Product flows
Coated chassis (coated_chassis)

Record the one product-specific coated chassis transferred to assembly.

  • Selected flow: Powder-coated metal lighting-product chassis
  • Flow property / unit: Mass / kg
  • Amount rule: Accepted coated chassis mass transferred to product_assembly
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_finish_outputs
  • Sources:
Waste flows
Pretreatment wastewater (pretreatment_wastewater)

Record the aqueous metal-pretreatment effluent transferred to the actual on-site or off-site treatment route.

  • Selected flow: Metal-pretreatment wastewater
  • Flow property / unit: Mass / kg
  • Amount rule: Metered discharge or tank balance, excluding clean stormwater
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finish_outputs
  • Sources:
Spent coating powder (spent_coating_powder)

Record unrecovered thermoset powder-coating waste leaving the process.

  • Selected flow: Spent thermoset polyester powder coating
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed collected powder sent to its documented waste route
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finish_outputs
  • Sources:
Elementary flows
Fossil carbon dioxide from curing (finish_fossil_co2)

Include direct fossil carbon dioxide only for on-site natural-gas combustion; upstream grid emissions are excluded from this row.

  • Selected flow: carbon dioxide (fossil) 08a91e70-3ddc-11dd-923d-0050c2490048
  • Flow property / unit: Mass 93a60a56-a3c8-11da-a746-0800200b9a66 / kg
  • Amount rule: Calculate from allocated gas quantity, supplier carbon factor, and documented oxidation factor using calc_fossil_co2
  • Value mode: Calculated value (calculated_value)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_finish_energy
  • Sources:

Process: Mechanical, optical, electrical, fuel-system, or sign assembly (product_assembly)

Inputs

Product flows
Uncoated chassis entering assembly (uncoated_chassis_for_assembly)

Use this row when the declared product is assembled without the on-site finishing process.

  • Selected flow: Uncoated metal lighting-product chassis ready for assembly
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed or BOM-derived mass issued to assembly
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_bom
  • Sources: pep-ecopassport-psr-0014-2023
Coated chassis entering assembly (coated_chassis_for_assembly)

Use this row only when surface_finishing produces the coated chassis.

  • Selected flow: Powder-coated metal lighting-product chassis ready for assembly
  • Flow property / unit: Mass / kg
  • Amount rule: Mass transferred from coated_chassis
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources:
Glass optical component (glass_optical_component)

Include the product-specific glass lens, diffuser, shade, or chimney when supplied with the declared product.

  • Selected flow: Formed soda-lime glass optical component
  • Flow property / unit: Mass / kg
  • Amount rule: Verified BOM quantity multiplied by measured component mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: us-doe-luminaires-definition, us-doe-led-lca-part2-2012
Polycarbonate optical component (polycarbonate_optical_component)

Include the one polycarbonate lens or diffuser actually supplied; do not combine it with other polymers.

  • Selected flow: Injection-moulded polycarbonate optical component
  • Flow property / unit: Mass / kg
  • Amount rule: Verified BOM quantity multiplied by measured component mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: us-doe-luminaires-definition
Steel mounting component (steel_mounting_component)

Include the steel bracket or mounting plate delivered with the declared finished product.

  • Selected flow: Zinc-coated steel mounting bracket
  • Flow property / unit: Mass / kg
  • Amount rule: Verified BOM quantity multiplied by measured component mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: us-doe-luminaires-definition
Copper wire (copper_wire)

Include insulated copper wire cut and installed in an electric product.

  • Selected flow: PVC-insulated copper wire
  • Flow property / unit: Mass / kg
  • Amount rule: Issued length multiplied by verified mass per metre, net of recorded offcuts
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: us-doe-luminaires-definition
LED module (led_module)

Include only when an LED module is delivered as part of the declared product.

  • Selected flow: LED module
  • Flow property / unit: Mass / kg
  • Amount rule: Verified BOM quantity multiplied by measured module mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: pep-ecopassport-psr-0014-2023, us-doe-led-lca-part2-2012
Electronic control gear (electronic_control_gear)

Include the specific driver, ballast, or control gear supplied with the product.

  • Selected flow: Electronic luminaire control gear
  • Flow property / unit: Mass / kg
  • Amount rule: Verified BOM quantity multiplied by measured control-gear mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: pep-ecopassport-psr-0014-2023, us-doe-luminaires-definition
Primary battery (primary_battery)

Include one declared battery chemistry only when the portable electric lamp is sold with that battery.

  • Selected flow: Alkaline manganese primary battery
  • Flow property / unit: Mass / kg
  • Amount rule: Supplied battery count multiplied by measured as-sold battery mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources:
Fuel reservoir (fuel_reservoir)

Include the reservoir when a non-electrical lamp is sold with a liquid-fuel container.

  • Selected flow: Steel liquid-fuel lamp reservoir
  • Flow property / unit: Mass / kg
  • Amount rule: Verified BOM quantity multiplied by measured empty reservoir mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources:
Lamp wick (wick)

Include the wick only when supplied with the non-electrical lamp.

  • Selected flow: Braided cotton lamp wick
  • Flow property / unit: Mass / kg
  • Amount rule: Supplied wick count or length multiplied by verified mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources:
Illuminated-sign face panel (illuminated_sign_face_panel)

Include the one product-specific sign or name-plate face panel supplied with an illuminated-sign product.

  • Selected flow: Printed acrylic illuminated-sign face panel
  • Flow property / unit: Mass / kg
  • Amount rule: Verified BOM quantity multiplied by measured panel mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources:
Epoxy adhesive (epoxy_adhesive)

Record the as-supplied two-part epoxy adhesive consumed in assembly.

  • Selected flow: Two-part epoxy adhesive
  • Flow property / unit: Mass / kg
  • Amount rule: Opening stock plus receipts minus closing stock and separately weighed uncured waste
  • Value mode: Calculated value (calculated_value)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: us-doe-led-lca-part2-2012
Lead-free solder paste (solder_paste)

Include only when soldering is performed under foreground control.

  • Selected flow: Tin-silver-copper lead-free solder paste
  • Flow property / unit: Mass / kg
  • Amount rule: Issued paste mass minus returned usable paste, allocated to accepted assemblies
  • Value mode: Calculated value (calculated_value)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_bom
  • Sources: us-doe-led-lca-part2-2012
Assembly electricity (assembly_electricity)

Record electricity for assembly tools, soldering, local extraction, and assembly-line support equipment.

  • Selected flow: Electricity 890a70b7-b677-4e2a-8a1b-7d017e0a10ae
  • Flow property / unit: Net calorific value 93a60a56-a3c8-11da-a746-0800200b9a66 / MJ
  • Amount rule: Submetered electricity or documented runtime allocation to the declared product
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_energy
  • Sources:
Waste flows
Elementary flows

Outputs

Product flows
Assembled unpacked product (assembled_unpacked_product)

Record each accepted assembled product transferred to final test before sales packaging.

  • Selected flow: Assembled unpacked lighting product
  • Flow property / unit: Mass / kg
  • Amount rule: Accepted assembly count multiplied by measured unpacked product mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_assembly_outputs
  • Sources:
Waste flows
Solder dross (solder_dross)

Record oxidized lead-free solder dross leaving the soldering operation.

  • Selected flow: Tin-silver-copper solder dross
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed dross transferred to the documented recycling or treatment route
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_outputs
  • Sources:
Rejected electronic assembly (rejected_electronic_assembly)

Record a failed populated electronic lighting assembly only when it leaves foreground control as waste.

  • Selected flow: Rejected populated luminaire electronic assembly
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed rejected electronic assemblies sent to the documented treatment route
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_outputs
  • Sources:
Elementary flows

Process: Final test, packing, and factory-gate release (final_testing_and_packaging)

Inputs

Product flows
Assembled product entering test (assembled_product_for_test)

Record the unpacked assembled product received from product_assembly.

  • Selected flow: Assembled unpacked lighting product entering final test
  • Flow property / unit: Mass / kg
  • Amount rule: Mass transferred from assembled_unpacked_product
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_test_pack_inputs
  • Sources:
Testing electricity (testing_electricity)

Record electricity used for burn-in, electrical safety, photometric, sign illumination, and packing equipment.

  • Selected flow: Electricity 890a70b7-b677-4e2a-8a1b-7d017e0a10ae
  • Flow property / unit: Net calorific value 93a60a56-a3c8-11da-a746-0800200b9a66 / MJ
  • Amount rule: Submetered test and packing electricity or documented test-power × duration allocation
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_test_energy
  • Sources:
Corrugated carton (corrugated_board_carton)

Include the corrugated fibreboard carton delivered with the product.

  • Selected flow: Corrugated fibreboard shipping carton
  • Flow property / unit: Mass / kg
  • Amount rule: Carton count multiplied by verified dry carton mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_test_pack_inputs
  • Sources: pep-ecopassport-psr-0014-2023, us-doe-led-lca-part2-2012
Polyethylene film bag (polyethylene_film_bag)

Include the one low-density polyethylene film bag supplied as primary protective packaging.

  • Selected flow: Low-density polyethylene protective film bag
  • Flow property / unit: Mass / kg
  • Amount rule: Bag count multiplied by verified film-bag mass
  • Value mode: Calculated value (calculated_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Calculated from collection (calculated_from_collection)
  • Collection protocol: cp_test_pack_inputs
  • Sources: pep-ecopassport-psr-0014-2023, us-doe-led-lca-part2-2012
Waste flows
Elementary flows

Outputs

Product flows
Finished lighting product (finished_lighting_product)

This is the declared reference-product output after acceptance testing and packing.

  • Selected flow: Finished packaged lighting or illuminated-identification product within this PCR scope
  • Flow property / unit: Mass 93a60a56-a3c8-11da-a746-0800200b9a66 / kg
  • Amount rule: Exactly 1 kg of accepted finished product; record corresponding item count and packaging mass
  • Value mode: Fixed value (fixed_value)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: 1 kg reference product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_final_outputs
  • Sources: un-cpc-3-structure-2025
Waste flows
Rejected finished product (rejected_finished_product)

Record a failed complete lighting product only when it leaves foreground control as waste rather than being reworked.

  • Selected flow: Rejected finished lighting product
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed failed finished products sent to the documented treatment route
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_final_outputs
  • Sources:
Corrugated carton scrap (corrugated_board_scrap)

Record corrugated fibreboard offcuts or damaged cartons leaving packing as waste.

  • Selected flow: Corrugated fibreboard carton scrap
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed carton scrap sent to the documented treatment route
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_final_outputs
  • Sources:
Polyethylene film scrap (polyethylene_film_scrap)

Record low-density polyethylene film offcuts or rejected bags leaving packing as waste.

  • Selected flow: Low-density polyethylene packaging film scrap
  • Flow property / unit: Mass / kg
  • Amount rule: Weighed film scrap sent to the documented treatment route
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per 1 kg finished packaged lighting product
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_final_outputs
  • Sources:
Elementary flows

7. Allocation and Co-product Handling

rule_idApplies toRulesource_ids
al_subdivideshared manufacturing linesPrefer subdivision, submetering, job records, or equipment-runtime records before allocation.pep-ecopassport-psr-0014-2023
al_physicalresidual shared inputs and outputsAllocate unresolved shared foreground quantities by a documented physical driver that causes the burden, such as machine time, coated surface area, test duration, or mass throughput.pep-ecopassport-psr-0014-2023
al_mass_fallbackco-products without a better causal driverApply output-mass allocation only when subdivision and a more specific physical relationship are not feasible; disclose all allocated products and the factor.pep-ecopassport-psr-0014-2023
al_scrapproduction scrap and recovered materialRecord scrap mass and its actual treatment or recycling input without avoided-burden credit inside the foreground gate; any substitution credit belongs to a separately declared downstream model.us-doe-led-lca-part2-2012
al_reworkreworked unitsKeep rework materials and energy in the foreground numerator and count only the finally accepted item in the reference output.

8. Foreground Data Collection, Calculation, and Quality Rules

Data Collection Protocols

protocol_idprocess_idflow_rolerecord_typeraw_fieldscollection_methodunitfrequencytemporal_coveragesite_scopeaggregation_rulequality_evidence
cp_finish_materialssurface_finishingchassis, coating, sodium hydroxide, and water inputspurchase, issue, stock, BOM, scale, and meter recordsmaterial identity; lot; opening stock; receipts; issues; returns; closing stock; chassis count and mass; water meterreconcile stock balance to finishing batches and verified BOMkgeach batch; monthly reconciliationrepresentative continuous 12 months or declared campaignall finishing lines serving declared productnet consumed quantity divided by kg of accepted reference productcalibrated scale/meter records; stock reconciliation; batch traveller
cp_finish_energysurface_finishingelectricity and natural gas inputs and direct combustion CO2utility submeters, invoices, runtime logs, and supplier fuel datameter start/end; kWh; m3; reference conditions; equipment runtime; product throughput; carbon factor; oxidation factorsubmeter or allocate by documented equipment runtime and throughputMJ; m3; kgeach batch or monthly meter periodsame period as production denominatorall finishing utilities and curing equipmentallocated utility divided by kg of accepted reference product; calculate direct CO2 separatelymeter calibration; invoice reconciliation; supplier fuel specification
cp_finish_outputssurface_finishingcoated chassis and finishing wastestransfer count, scale, effluent meter, tank, and waste manifest recordsaccepted chassis count and mass; effluent mass or volume; powder waste mass; destinationreconcile output, inventory change, and waste to input material balancekgeach batch and each waste shipmentsame period as finishing inputsall finishing outputs under site controltotal output or waste divided by kg of accepted reference producttransfer tickets; scale checks; discharge meter; waste manifests
cp_assembly_bomproduct_assemblyproduct-specific assembly inputscontrolled BOM, issue/return, component count, mass and length recordsmodel; BOM revision; component identity; quantity; unit mass; wire length and mass per metre; opening/closing consumable stockverify BOM against as-built sample and reconcile issued consumableskgeach model revision; each production batchrepresentative 12 months or declared campaignall assembly lines serving declared productnet component or consumable mass divided by kg of accepted reference productapproved BOM; change control; calibrated component weights; stock reconciliation
cp_assembly_energyproduct_assemblyassembly electricitysubmeter and equipment-runtime recordskWh; meter period; equipment power; runtime; line throughputsubmeter or allocate by documented runtimeMJbatch or monthlysame period as assembly outputall assembly equipment and local extractionallocated electricity divided by accepted assembliesmeter calibration; runtime log; invoice reconciliation
cp_assembly_outputsproduct_assemblyaccepted assemblies and assembly wastesproduction count, mass, reject and waste recordsaccepted count; unpacked mass; solder dross mass; rejected assembly mass; dispositionreconcile transfers, rework, rejects, and waste to issued inputskgeach batch and each waste shipmentsame period as assembly inputsall assembly outputs under site controloutput or waste divided by kg of accepted reference productbatch traveller; calibrated scale; reject log; waste manifest
cp_test_pack_inputsfinal_testing_and_packagingassembled product and packaging inputstransfer count, packaging BOM, issue and component-weight recordsassembly count/mass; carton count/mass; bag count/mass; packaging revisionreconcile issued packaging to packed output and packaging scrapkgeach batchrepresentative 12 months or declared campaignall final-test and packing linesnet input divided by kg of accepted packed productpacking BOM; component weight checks; issue/return records
cp_test_energyfinal_testing_and_packagingtesting and packing electricitytest logs, submeter and equipment power-time recordskWh; test type; power; duration; tested units; packing runtimesubmeter or calculate power × time and reconcile to the meterMJeach test batch or monthlysame period as accepted packed outputall test rigs and packing equipmentallocated electricity divided by kg of accepted packed producttest-system calibration; meter record; test log
cp_final_outputsfinal_testing_and_packagingaccepted reference product and final wastesacceptance, packing, scale, reject and waste recordsaccepted item count; net and gross mass; failed count/mass; rework; carton scrap; film scrap; destinationcount accepted products and weigh each segregated waste streamitem; kgeach batch and each waste shipmentrepresentative 12 months or declared campaignall factory-gate outputs for declared productexactly 1 kg accepted product as reference; each waste divided by accepted product massacceptance report; scale calibration; reject disposition; waste manifest

Calculation Rules

rule_idApplies toFormula or ruleInputsOutputsource_ids
calc_bom_masscounted componentscomponent mass per kg reference product = net component count × verified unit mass ÷ accepted finished-product mass in kgBOM quantity; unit mass; accepted finished-product masskg component per kg reference product
calc_stock_consumptioncoating, adhesive, and solderconsumed mass = opening stock + receipts − returns − closing stock − separately recovered reusable materialstock and issue recordskg consumed per kg reference product
calc_energy_allocationshared equipment energyallocated energy = metered period energy × declared causal allocation factor ÷ accepted finished-product mass in kgmeter reading; runtime or throughput driver; accepted finished-product massMJ per kg reference productpep-ecopassport-psr-0014-2023
calc_fossil_co2on-site natural-gas combustiondirect fossil CO2 = allocated gas quantity × documented supplier carbon factor × oxidation factor; preserve factor units and reference conditionsgas volume; carbon factor; oxidation factorkg fossil CO2 per kg reference product
calc_transfer_balanceinternal intermediatesprior-process accepted output = next-process input + separately recorded inventory change + rework + losstransfer and inventory recordsreconciled kg internal intermediate
calc_final_yieldfinal product and rejectsfirst-pass and final yield must be calculated from tested, reworked, rejected, and accepted unit counts; the reference output remains one finally accepted itemtest and disposition countsitem yield disclosure and kg reject per accepted item

Data Quality Requirements

requirement_idApplies toRequirementEvidence
dq_identitydeclared productFreeze the model/BOM/packaging revision and all required qualifiers for the reporting period; aggregate models only with a disclosed production-weighting method.approved specifications, BOM, model list, and production volumes
dq_completenessinventoryReconcile every purchased component and consumable in the sale configuration, each energy meter, each internal transfer, and each segregated output; explain zero, excluded, and unavailable rows.mass/energy reconciliation and completeness checklist
dq_measurementmeasured quantitiesUse calibrated meters and scales or document equipment-runtime estimates and their uncertainty when direct measurement is unavailable.calibration certificates, meter logs, and estimation records
dq_temporalforeground dataUse a continuous representative 12-month period when available; otherwise disclose the campaign dates, seasonality, downtime, and extrapolation.dated production, utility, and waste records
dq_supplier_matchupstream datasetsMatch purchased flows to actual material, component, chemistry, geography, technology, and delivery state; disclose every proxy.supplier specifications and dataset mapping review
dq_conditional_routescategory variantsDemonstrate why each conditional process or row is present or absent for the declared product; do not average incompatible electric, battery, fuel, sign, or optical configurations.route declaration and signed BOM review
dq_uuid_statusTiangong identitiesPreserve UUID-empty rows as unresolved until a public state-100 identity is audited; do not promote a parts flow or technology-specific component as the finished reference product.manifest unresolved list and finalized UUID-search receipt

9. Validation Rules

rule_idApplies toRulesource_ids
vr_referencereference flowVerify exactly 1 kg of accepted finished product, matching model/BOM/packaging revision, is the quantitative reference and that item count and packaging mass are declared.un-cpc-3-structure-2025
vr_scopeproduct identityConfirm the declared product is within the covered product list and is not a vehicle/cycle lamp, public-space/thoroughfare fitting, separate light source, Christmas-tree set, separately classified LED-only luminaire, or part.un-cpc-3-structure-2025
vr_component_setsale configurationConfirm included light source, control gear, battery, mounting parts, fuel reservoir, wick, sign panel, and packaging match the product actually sold.pep-ecopassport-psr-0014-2023, us-doe-luminaires-definition
vr_atomic_flowsprocess inventoryReject any row that combines materials, utilities, fuels, packaging, wastes, or emissions; every selected flow must denote one atomic exchange.
vr_balanceforeground processesReconcile material inputs, internal transfers, product, rework, inventory change, and segregated wastes; investigate unexplained imbalance before publication.
vr_energyelectricity and natural gasCheck meter period, production denominator, unit conversion, grid geography, gas reference conditions, and allocation driver.
vr_conditionalconditional processes and rowsRequire an explicit applicability result for finishing, LED module, control gear, battery, fuel reservoir, wick, sign panel, and each packaging component.
vr_comparabilitydownstream useReject comparative claims based only on mass; require compatible light output or illuminated function, lifetime, operating pattern, product state, and system boundary.pep-ecopassport-psr-0014-2023, us-doe-led-lca-part2-2012

10. Published Dataset Profile

FieldValue
dataset_rolesecondary_dataset; may be used as background_dataset only for the declared product configuration and geography
downstream_useForeground product-footprint construction and downstream process or lifecyclemodel projections for a matching finished lighting or illuminated-identification product
allowed_useFactory-gate modelling when product subtype, BOM, included components, performance qualifiers, mass, packaging, technology, geography, and period match the intended use
excluded_useFunctional comparison across unlike product subtypes; unqualified substitution for separate light sources, parts, LED-only luminaires classified elsewhere, public-space lighting, vehicle/cycle lamps, use-stage electricity/fuel, installation, maintenance, or end-of-life
required_metadatacanonical PCR id; model/BOM/packaging revisions; all reference-flow qualifiers; production site and period; foreground boundary; conditional-route decisions; allocation; accepted item count; net/gross mass; data-source mapping; unresolved UUIDs and ranges
required_quality_disclosuremeter and scale coverage; temporal and site representativeness; mass/energy reconciliation; supplier-data quality; proxies; cut-offs; rework and reject treatment; background-dataset versions; uncertainty and data gaps
update_triggerChange in product subtype, BOM, light source/control gear/battery/fuel system, sign panel, finishing route, packaging, site, energy supply, allocation, service-life declaration, or a cumulative production mix change that makes the dataset unrepresentative

11. Data Sources

Source idTypeReferenceUsed for
un-cpc-3-structure-2025official_guidanceUnited Nations Statistics Division, CPC Version 3.0 Structure, 30 June 2025. https://unstats.un.org/unsd/classifications/Econ/Download/In%20Text/CPC_Ver_3.0_Structure_30Jun2025.csv (retrieved 2026-09-04)Official CPC 46531 identity, inclusions, exclusions, and distinction from adjacent lighting products.
pep-ecopassport-psr-0014-2023standardPEP ecopassport, PSR-0014-ed2-EN-2023 07 13, Product Specific Rules for Luminaires. https://register.pep-ecopassport.org/documents (retrieved 2026-09-04)Grid-connected luminaire subset definition; reference-flow qualifiers; component completeness; manufacturing-stage boundary; co-product allocation.
us-doe-led-lca-part2-2012official_guidanceU.S. Department of Energy, Life-Cycle Assessment of Energy and Environmental Impacts of LED Lighting Products, Part 2: LED Manufacturing and Performance, PNNL-21443, June 2012. https://www.energy.gov/documents/2012ledlca-pt2pdf-0 (retrieved 2026-09-04)Lamp manufacturing boundary, raw materials and components, assembly/manufacturing energy, packaging, and performance normalization context.
us-doe-luminaires-definitionofficial_guidanceU.S. Department of Energy, Luminaires. https://www.energy.gov/cmei/buildings/luminaires (retrieved 2026-09-04)Functional definition and mechanical, optical, electrical, and electronic luminaire component types.

Raw downloads

These files are byte-identical to the canonical files for this revision in the repository.

Structured rule index

This index comes from verified structured.yaml and retains the canonical English rule text.

System boundary rules · 4
Rule IDApplies toRuleSource IDs
sb_gate_boundaryall foreground processesInclude receipt-to-factory-gate activities controlled by the manufacturer: applicable finishing, assembly, factory tests, packing, rework, rejects, and on-site waste generation. Exclude installation, downstream distribution, use, maintenance, and end-of-life.pep-ecopassport-psr-0014-2023, us-doe-led-lca-part2-2012
sb_component_completenessproduct bill of materialsInclude every component delivered with the product or needed for the declared sale configuration, and state explicitly whether the light source, control gear, battery, mounting parts, fuel reservoir, wick, or sign panel is supplied.pep-ecopassport-psr-0014-2023, us-doe-luminaires-definition
sb_upstream_connectionpurchased inputsModel upstream raw-material, component, energy, water, and packaging production in linked background datasets; do not count those upstream processes again as foreground manufacturing.us-doe-led-lca-part2-2012
sb_variant_conditionconditional routesInstantiate only the rows and processes physically present for the declared product. Mark demonstrably absent conditional rows not_applicable; never substitute another material, battery chemistry, fuel, or component.un-cpc-3-structure-2025
Allocation rules · 5
Rule IDApplies toRuleSource IDs
al_subdivideshared manufacturing linesPrefer subdivision, submetering, job records, or equipment-runtime records before allocation.pep-ecopassport-psr-0014-2023
al_physicalresidual shared inputs and outputsAllocate unresolved shared foreground quantities by a documented physical driver that causes the burden, such as machine time, coated surface area, test duration, or mass throughput.pep-ecopassport-psr-0014-2023
al_mass_fallbackco-products without a better causal driverApply output-mass allocation only when subdivision and a more specific physical relationship are not feasible; disclose all allocated products and the factor.pep-ecopassport-psr-0014-2023
al_scrapproduction scrap and recovered materialRecord scrap mass and its actual treatment or recycling input without avoided-burden credit inside the foreground gate; any substitution credit belongs to a separately declared downstream model.us-doe-led-lca-part2-2012
al_reworkreworked unitsKeep rework materials and energy in the foreground numerator and count only the finally accepted item in the reference output.
Validation rules · 8
Rule IDApplies toRuleSource IDs
vr_referencereference flowVerify exactly 1 kg of accepted finished product, matching model/BOM/packaging revision, is the quantitative reference and that item count and packaging mass are declared.un-cpc-3-structure-2025
vr_scopeproduct identityConfirm the declared product is within the covered product list and is not a vehicle/cycle lamp, public-space/thoroughfare fitting, separate light source, Christmas-tree set, separately classified LED-only luminaire, or part.un-cpc-3-structure-2025
vr_component_setsale configurationConfirm included light source, control gear, battery, mounting parts, fuel reservoir, wick, sign panel, and packaging match the product actually sold.pep-ecopassport-psr-0014-2023, us-doe-luminaires-definition
vr_atomic_flowsprocess inventoryReject any row that combines materials, utilities, fuels, packaging, wastes, or emissions; every selected flow must denote one atomic exchange.
vr_balanceforeground processesReconcile material inputs, internal transfers, product, rework, inventory change, and segregated wastes; investigate unexplained imbalance before publication.
vr_energyelectricity and natural gasCheck meter period, production denominator, unit conversion, grid geography, gas reference conditions, and allocation driver.
vr_conditionalconditional processes and rowsRequire an explicit applicability result for finishing, LED module, control gear, battery, fuel reservoir, wick, sign panel, and each packaging component.
vr_comparabilitydownstream useReject comparative claims based only on mass; require compatible light output or illuminated function, lifetime, operating pattern, product state, and system boundary.pep-ecopassport-psr-0014-2023, us-doe-led-lca-part2-2012
Processes and inputs/outputs · 3
Process IDProcess nameInput flowsOutput flows
surface_finishingChassis pretreatment and powder coating64
product_assemblyMechanical, optical, electrical, fuel-system, or sign assembly153
final_testing_and_packagingFinal test, packing, and factory-gate release44

Complete field inspector

Loads this record’s complete manifest and structured projection on demand; values are never truncated. Requires JavaScript.

On this page

1. Scope and Applicability2. Product Category Identity3. Reference Flow4. Measurement and Unit Rules5. System BoundaryBoundary Abstraction6. Process Inventory StructureProcess MapProcess: Chassis pretreatment and powder coating (surface_finishing)InputsProduct flowsUncoated metal chassis (uncoated_metal_chassis)Thermoset powder coating (powder_coating_material)Alkaline pretreatment chemical (finish_sodium_hydroxide)Finishing water (finish_process_water)Finishing electricity (finish_electricity)Curing natural gas (finish_natural_gas)Waste flowsElementary flowsOutputsProduct flowsCoated chassis (coated_chassis)Waste flowsPretreatment wastewater (pretreatment_wastewater)Spent coating powder (spent_coating_powder)Elementary flowsFossil carbon dioxide from curing (finish_fossil_co2)Process: Mechanical, optical, electrical, fuel-system, or sign assembly (product_assembly)InputsProduct flowsUncoated chassis entering assembly (uncoated_chassis_for_assembly)Coated chassis entering assembly (coated_chassis_for_assembly)Glass optical component (glass_optical_component)Polycarbonate optical component (polycarbonate_optical_component)Steel mounting component (steel_mounting_component)Copper wire (copper_wire)LED module (led_module)Electronic control gear (electronic_control_gear)Primary battery (primary_battery)Fuel reservoir (fuel_reservoir)Lamp wick (wick)Illuminated-sign face panel (illuminated_sign_face_panel)Epoxy adhesive (epoxy_adhesive)Lead-free solder paste (solder_paste)Assembly electricity (assembly_electricity)Waste flowsElementary flowsOutputsProduct flowsAssembled unpacked product (assembled_unpacked_product)Waste flowsSolder dross (solder_dross)Rejected electronic assembly (rejected_electronic_assembly)Elementary flowsProcess: Final test, packing, and factory-gate release (final_testing_and_packaging)InputsProduct flowsAssembled product entering test (assembled_product_for_test)Testing electricity (testing_electricity)Corrugated carton (corrugated_board_carton)Polyethylene film bag (polyethylene_film_bag)Waste flowsElementary flowsOutputsProduct flowsFinished lighting product (finished_lighting_product)Waste flowsRejected finished product (rejected_finished_product)Corrugated carton scrap (corrugated_board_scrap)Polyethylene film scrap (polyethylene_film_scrap)Elementary flows7. Allocation and Co-product Handling8. Foreground Data Collection, Calculation, and Quality RulesData Collection ProtocolsCalculation RulesData Quality Requirements9. Validation Rules10. Published Dataset Profile11. Data Sources