Mine facility construction and physical delivery · Calculation Rules

Lifecycle status
Candidate
Content maturity
Authored methodology
Current version
0.1.0Last updated
Readiness
Review required

Methodology and translation states come from the source record; publishing this website does not change their review status.

Content languages

zh-CN · Aligned
Status, classification and source details

Readiness

  • Warnings methodology_not_reviewed Authored methodology is candidate guidance and still requires methodology review.

Classification mapping

CPC 3.0:53261 · exact

Source

Calculation Rules

rule_idApplies toFormula or ruleInputsOutputsource_ids
delivery_reconciliationall inventory rowsKeep each actual attributable exchange total in its declared unit per declared reference flow. Reconcile receipts, stock changes, returns, internal batch transfers, installed material, real losses and outgoing streams. Separate independent accepted facilities by actual direct subdivision before reporting one delivery; no default mix, per-facility mass, density, loss or life.cp_acceptance; cp_earth; cp_blast; cp_batch; cp_support; cp_civil; cp_install; cp_utilities; cp_water; cp_wastesame-unit exchange total per declared reference flowwa-ground-control-2019; epa-concrete-washout-2012
preserve_numerator_unitselectricity_lv_cn; electricity_mv_cn; electricity_other; diesel; treated_process_water; low_voltage_cable; road_freightMaintain the complete facility denominator. Electricity kWh becomes MJ using 3.6 MJ/kWh; L becomes m3 using 0.001 m3/L; road payload t times actual km gives t*km, with 1000 kg/t. For mass/volume/count/length relations retain actual measured/certified same-state density, unit mass or geometry with units and uncertainty. Public reference properties remain unchanged.cp_utilities; cp_water; cp_transport; cp_installsame-unit exchange total per declared reference flow
asset_attributionexcavator_asset; drill_asset; crane_asset; formwork_plywood; steel_meshFor included reusable asset manufacture, multiply actual same-configuration asset mass/count by the evidenced dimensionless current service share. Current and total service have matching units and real supported boundaries; retain all prior and other uses so cumulative shares do not exceed one. Permanent delivered material is its actual full included quantity once. This attributes an input asset, not a conversion of the facility reference to kg.cp_assetsattributed asset input per declared reference flow
environmental_quantificationfossil_co2; nitrogen_monoxide; nitrogen_dioxide; pm25; pm_2_5_10; pm_unspecified; groundwater_abstraction; freshwater_release; seawater_releaseUse supported external substance/fraction release or resource withdrawal totals, preserving actual medium and units. Air mass requires real concentration times corresponding flow/time or actual activity times an independently supported species/control factor. Water pollutants require actual concentration times corresponding actual discharge volume with units. Fuel carbon balance needs measured fossil fraction/oxidation; it supplies no NOx split or PM factor. Retain nonoverlapping fractions and water destinations; missing evidence is unknown, not zero.cp_air; cp_water; cp_utilitiessupported release or withdrawal per declared reference flowifc-mining-2007
joint_works_attributionmine_excavation; reference_mine_facilityUse actual separate stage totals wherever causal construction and production are observable. For any inseparable jointly beneficial work, apply the reviewed actual causal driver with all recipients and denominator documented in cp_allocation; retain exported development ore as a real output and do not credit hypothetical avoided mining. Later mineral inventories must reference the resulting construction burden once.cp_allocation; cp_earth; cp_acceptancereviewed attributed construction exchange total per declared reference flowplatreef-shaft-case-2025

Data Quality Requirements

requirement_idApplies toRequirementEvidence
entity_completereference_mine_facilityRetain the entire accepted functional scope and all real route stages, geometry, configuration and tests; distinguish actual completed work from proposed mine expansions.cp_acceptance; as-built survey and asset/interface schedule
identity_and_unitsall inventory rowsVerify each actual material/substance/component state and public reference property/unit; retain geography/voltage/medium/CAS/fossil/size conditions. Blank UUIDs require row-level resolution before deployment as confirmed identities.supplier/assay/site evidence and public identity references
time_and_sitedatasetCover the real construction and test campaign at the actual site, including returns, rework, dewatering and temporary operation; explain subcontract gaps and unmeasured intervals.all cp records with dates, calibration and coverage
assets_and_joint_workexcavator_asset; drill_asset; crane_asset; formwork_plywood; mine_excavationDocument supported total asset service and all attribution recipients; review unknown denominator and actual/forecast ore interfaces, retaining cumulative share conservation and sensitivity.cp_assets; cp_allocation; complete persistent ledgers
environmental_coveragesite_utilities; construction_wasteTrack actual external air/liquid pathways separately from workplace exposure and waste transfer. Add significant real geological gas, dissolved species, land and noise/vibration coverage with correct metrics; declare measurement/identity gaps rather than asserting total coverage.cp_air; cp_water; cp_waste; location/time and method evidence

9. Validation Rules

rule_idApplies toRulesource_ids
v_referencereference_mine_facilityRequire one complete physically accepted facility and all relevant qualifiers; reference name and output-row name match exactly, output is 1 item and every collection/inventory denominator is per declared reference flow. A count basis alone does not demonstrate applicability or interchangeable performance.
v_routeall inventory rowsCheck the actual shaft/drift/pit/headframe/station route and all significant materials, mixtures, permanent devices, plant and tests. Mark a conditional exchange absent only with evidence. Actual unlisted chemistry/components get separate atomic rows; mixture alternatives and internal transfers are not duplicate purchases.
v_units_identityall inventory rowsCheck actual supply gates, country/voltage, substance/CAS/origin, medium/submedium, particle size and reference property/unit relations. No false conversion from Volume/Length/Count to Mass, unresolved reference product UUID remains a declared candidate gap, and public official Chinese names remain aligned.
v_balancesmine_excavation; site_batching; site_utilities; construction_wasteReconcile actual excavation/reuse/export, each fresh mixture, fuel/stock, liquid inputs/outputs and waste disposition. Distinguish natural withdrawal, consumption, treatment transfer and direct recipient release; PM fractions and molecular NO/NO2 cannot be replaced by totals/equivalents or workplace concentrations.
v_allocationdatasetVerify one persistent cross-project asset ledger and supported share denominator; cumulative manufacture attribution at most one. Review facility/ore-production joint activities and prevent mineral models counting the same development burden again. Unproved mathematical/causal relationships remain review.
v_coveragedatasetReport performed/skipped checks, source-bound measurement/identity gaps, uncertainty and stage coverage. Neither accepted construction nor a passed structural check grants methodology/scientific approval. Do not label foreground as complete cradle-to-gate, whole life or total environmental coverage without independent complete evidence.

10. Published Dataset Profile

FieldValue
dataset_roleforeground construction and physical delivery dataset for the defined mining facility
downstream_usesecondary_dataset; background_dataset
allowed_useUse as one explicitly bounded mining infrastructure input or comparison of equivalent configured facility deliveries with compatible geology, function, geometry, interfaces and coverage; later mineral production uses only justified attributed construction shares.
excluded_useGeneric ore-production/emission factor, construction-service factor, building/TBM/winder manufacturing rule, cost-based facility proxy, universal shaft recipe, unqualified cross-mine comparison or automatic whole-life/safety approval.
required_metadatasite/project and facility identity; mine type and actual geology/hydrogeology; actual construction route; complete spatial and functional extent; shaft/drift/pit/tower/station geometry where applicable; support/lining and permanent equipment configuration; material/fuel/water states; measured handling/access/ventilation/water-control function and test criteria; as-built survey and acceptance state/dates; retained/removed assets; construction/upstream/transport/later-phase interfaces; shared asset/ore-development attribution; omitted/unresolved environmental and identity coverage
required_quality_disclosureActual foreground and upstream/transport coverage, identity gaps, source edition/case limits, recipes/measurements, unmeasured species and environmental metrics, actual/forecast activity and asset shares, allocation sensitivity and later phases excluded.
update_triggerFacility/route/geology/configuration or acceptance change; new supplier/material/property identity; revised plant service/ore attribution; significant water/gas/land/noise evidence; review of technical source edition or unresolved coverage.

11. Data Sources

Source idTypeReferenceUsed for
unsd-cpc-3-2025official_guidanceUN Statistics Division. CPC Version 3.0 Explanatory Notes, 30 June 2025, printed/PDF p.281, subclass 53261 and adjacent 53262/53269. https://unstats.un.org/unsd/classifications/Econ/Download/In%20Text/CPC_Ver_3.0_Exp_Notes_30Jun2025.pdfNon-building mining category and adjacent entity separation only; no engineering amount or LCA approval.
wa-ground-control-2019official_guidanceDepartment of Mines, Industry Regulation and Safety, Western Australia. Ground control management in Western Australian mining operations – guideline, 2019; printed pp.11 and 26 (PDF pp.17 and 32), with hydrogeology/route context. https://www.worksafe.wa.gov.au/system/files/documents/2025-02/MSH_GL_GroundControl.pdfQualitative opening/ground-control/support route context. WA jurisdiction and 2019 edition; no support spacing/threshold, recipe, life or current compliance rule imported.
platreef-shaft-case-2025literatureIvanhoe Mines. Platreef Phase 2 and Phase 3 expansion studies news release, 18 February 2025; printed/PDF p.10, shaft/headframe/winder and muck route; pp.8–9 identify development/production interface. https://www.ivanhoemines.com/wp-content/uploads/20250218-Platreef-2025-FS-PEA-ABF-1.pdfDeveloper primary technical case; distinguish completed observations and then-proposed works/forecasts. South African route/interface illustration only; no case dimensions/capacity, mix, dates or intensity used as defaults.
ifc-mining-2007official_guidanceIFC/World Bank Group. Environmental, Health, and Safety Guidelines for Mining, 10 December 2007; printed/PDF pp.2–4 and 12–13 for development phases, water/effluent, dust/gases, noise/vibration and construction activity interfaces. https://www.ifc.org/content/dam/ifc/doc/2000/2007-mining-ehs-guidelines-en.pdfQualitative actual-pathway and source/control prompts across mining phases; apply only real construction activities. No universal emission factor, water chemistry, hydraulic design interval, numeric limit or compliance approval adopted.
epa-concrete-washout-2012official_guidanceUS EPA. Stormwater Best Management Practice: Concrete Washout, EPA-833-F-11-006, February 2012, PDF p.1. https://www.epa.gov/sites/default/files/2015-11/documents/concretewashout_0.pdfHistorical qualitative actual batching/washout mechanism and liquid/solid separation; no default pH, concrete recipe, recovery rate or regulatory approval.

Raw downloads

These files are byte-identical to the canonical files for this revision in the repository.