TianGong PCR产品类别规则

Electrical resistors (except heating resistors)

Electrical resistors (except heating resistors): This PCR applies to foreground production of finished electrical resistors in CPC 47120, including fixed resistors and…

Lifecycle status
Candidate
Content maturity
Authored methodology
Current version
No published version
Readiness
Review required
Last updated

Methodology and translation states come from the source record; publishing this website does not change their review status.

Content languages

zh-CN · Aligned
Status, classification and source details

Readiness

  • Warnings methodology_not_reviewed Authored methodology is candidate guidance and still requires methodology review.

Classification mapping

CPC 3.0:47120 · exact

Source

1. Scope and Applicability

This PCR applies to foreground production of finished electrical resistors in CPC 47120, including fixed resistors and variable resistors such as rheostats and potentiometers, but excluding heating resistors. It covers discrete surface-mount, leaded, chassis-mounted, preset, single-turn, and multi-turn products when their principal function is electrical resistance or adjustable electrical resistance.

The production route begins with purchased constituent materials, parts, and same-category intermediate products at the declared factory gate and ends with tested, marked, packaged finished resistors at the plant gate. The producer must declare the resistor family and technology actually represented; route-specific operations that do not occur must not be modelled as if they did.

2. Product Category Identity

FieldValue
canonical_pcr_idpcr.metal-products-machinery-and-equipment.radio-television-and-communication-equipment-and-apparatus.electrical-resistors-except-heating-resistors
classification_refsCPC 3.0 47120, Electrical resistors (except heating resistors), exact
covered_productsFinished fixed resistors and resistor networks; film, foil, composition, wirewound, and metal-strip resistor technologies; variable resistors including rheostats, potentiometers, presets, and multi-turn types
excluded_productsHeating resistors; unassembled resistive elements or generic resistive and conductive materials; semiconductor devices, capacitors, and other broader electronic-component groups; resistor-containing assemblies whose principal function is not the resistor; installation, use, maintenance, and end-of-life activities
representative_productA finished, electrically tested resistor conforming to the declared fixed or variable resistor specification
production_routeProduction mix, at plant, covering material preparation, resistive-element formation, termination and mechanical assembly, and finishing, testing, marking, and pack-out; non-applicable route steps are declared
market_stateFinished product, manufactured and released for sale at the plant gate

3. Reference Flow

FieldValue
WhatFinished electrical resistors, except heating resistors, with the declared product and performance specification
How much1 kg net mass of accepted finished resistor product
How wellConforming to the declared fixed or variable type, technology, resistance value or adjustment range, tolerance, rated dissipation, temperature coefficient or stability class, termination, housing or package, and applicable electrical inspection criteria
How long or cycleOne production lot or reporting-period production campaign represented at the plant gate; service life is not part of the reference quantity
reference_flow_linkThe functional unit is realized by the Tiangong product flow and mass reference below; the foreground package normalizes accepted output to 1 kg
FieldValue
Reference amount1 kg
Reference product flowElectrical resistors (except heating resistors) 9bee079d-ab55-44db-b1a4-72d61a856d61
Reference flow propertyMass 93a60a56-a3c8-11da-a746-0800200b9a66
Reference unit groupUnits of mass 93a60a57-a4c8-11da-a746-0800200c9a66
Reference unitkg
Required qualifiersfixed or variable resistor family; resistive-element technology; surface-mount, leaded, chassis-mounted, preset, single-turn, or multi-turn form; resistance value or adjustment range; tolerance; rated dissipation; temperature coefficient or stability class; termination and housing or package; production geography and period; production mix; plant gate; net product mass; conformity basis

When constructing a foreground data package, the items listed in Required qualifiers must be declared in dataset metadata, process notes, reference flow comment, product description, or an equivalent data package field. Missing required qualifiers make the reference flow definition incomplete for that data package.

4. Measurement and Unit Rules

rule_idApplies toRequired propertyRequired unitRule
reference_massaccepted finished resistor outputMass 93a60a56-a3c8-11da-a746-0800200b9a66kgNormalize all inventory quantities to 1 kg net mass of accepted finished product at the declared plant gate; packaging is inventoried separately and is not included in net product mass.
piece_to_mass_conversionrecords available only as item countsMass 93a60a56-a3c8-11da-a746-0800200b9a66kgConvert counts to mass using a measured, product-specific average net mass from a documented sample of the represented lot; record sample size, total sample mass, scale identity, and calculation.
wet_or_solution_massprocess chemicals reported as solutionsMass 93a60a56-a3c8-11da-a746-0800200b9a66kgRecord delivered solution mass and concentration separately; do not substitute active-substance mass for total purchased solution mass without an explicit calculation record.
internal_rework_massinternally recirculated resistor material or unitsMass 93a60a56-a3c8-11da-a746-0800200b9a66kgTrack internal rework separately from external inputs and saleable output so that recirculation is not double-counted.

5. System Boundary

rule_idApplies toRulesource_ids
boundary_gate_to_gateforeground productionInclude constituent-material and part receiving and preparation, resistive-element formation, termination and mechanical assembly, route-applicable coating or encapsulation, electrical testing, marking, and pack-out through accepted product at the plant gate.vishay-fixed-resistor-basics-2008
boundary_route_declarationall represented product familiesDeclare whether the product is fixed or variable and identify the actual technology and form; include contact, wiper, adjustment-mechanism, shaft, housing, or multi-turn assembly only when present, and do not add absent route steps.iec-60115-1-2020; iec-60393-1-2008; vishay-fixed-resistor-basics-2008
boundary_upstream_linkspurchased products and servicesLink purchased substrates, cores, resistive materials, wires or foils, termination and contact materials, housings, coatings, encapsulants, process chemicals, packaging, energy carriers, water, and external treatment services to suitable upstream datasets; retain supplier-primary data where available.eu-pef-2021-2279
boundary_direct_releasessite-controlled operationsInclude measured or permitted direct air emissions, wastewater releases, and wastes caused by included processes, with the treatment or destination declared.eu-pef-2021-2279
boundary_exclusionsdownstream and capital activitiesExclude distribution beyond the plant gate, installation, use, maintenance, and end of life. Exclude capital goods only when the study method permits and disclose that exclusion; do not exclude material or energy flows merely because they are small.eu-pef-2021-2279

Boundary Abstraction

FieldValue
declared_starting_conditionpurchased constituent materials, parts, utilities, and any same-category intermediate resistor product received at the manufacturing site
starting_condition_roleforeground gate-to-gate starting inventory with upstream links and declared supplier or internal-production status
product_classification_scopeCPC 3.0 47120, including fixed and variable electrical resistors and excluding heating resistors
recursive_input_ruleA same-category resistor input is recorded as an explicit product input with its mass and production status; its upstream burden is linked once and is not recreated by recursively applying this PCR inside the same foreground package.
upstream_dataset_requirementUse geographically, temporally, and technologically representative upstream datasets for all material purchased inputs, utilities, packaging, and external treatment services; disclose proxies and data gaps.
disclosureDeclare product family, technology, form, plant location, reporting period, included production stages, same-category inputs, outsourced steps, packaging basis, exclusions, and upstream dataset choices.

6. Process Inventory Structure

Process Map

process_idprocess_nameinclusioninclusion_conditionrolequantitative_reference
material_receiving_and_preparationMaterial receiving and preparationrequiredforeground material preparationkg prepared constituent materials and parts
resistive_element_formationResistive-element formationrequiredInclude the declared film, foil, composition, wirewound, metal-strip, or other qualifying resistor route; route-specific deposition, printing, pressing, winding, etching, cutting, and trimming operations apply only when performed.foreground component manufacturekg accepted formed resistive elements
termination_and_mechanical_assemblyTermination and mechanical assemblyrequiredInclude fixed-resistor termination and body assembly; additionally include contact, wiper, adjustment mechanism, shaft, housing, or multi-turn assembly for applicable variable resistors.foreground product assemblykg assembled resistors before final finishing and testing
finishing_testing_and_packoutFinishing, electrical testing, marking, and pack-outrequiredInclude route-applicable coating, encapsulation, curing, plating, marking, screening, final inspection, and packaging.foreground finishing and releasekg accepted finished electrical resistors

Process: Material receiving and preparation (material_receiving_and_preparation)

Inputs

Product flows
Purchased constituent materials and parts (purchased_constituent_materials_and_parts)

Record all purchased substrates or cores, resistive materials, wire, foil or strip, termination and contact materials, housings, adjustment parts, coatings, encapsulants, process chemicals, and other parts that enter production. Preserve product-family and supplier-lot identity.

  • Selected flow: Select supplier- and material-specific product flows for each constituent material or part
  • Flow property / unit: Mass / kg
  • Amount rule: measured received or issued mass, corrected for documented returns and stock changes
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per kg accepted prepared material and parts issued to included production
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_receiving_material_records
  • Sources: vishay-fixed-resistor-basics-2008
  • Range: Provisional material-input screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0.1
    • Upper: 20
    • Unit: kg/kg accepted prepared material and parts
    • Basis: per kg accepted prepared material and parts issued to production; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Waste flows

Outputs

Product flows
Prepared materials and parts issued to production (prepared_materials_and_parts)

Record weighed materials and parts released from receiving, preparation, mixing, cutting, or kitting to the next included process. Keep route-specific material groups separately identifiable.

  • Selected flow: Select material- or part-specific intermediate product flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured issued mass plus documented prepared stock change
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: process reference
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_prepared_material_output
  • Sources:
Waste flows
Rejected incoming material and preparation waste (receiving_and_preparation_waste)

Record rejected, spilled, trimmed, expired, or otherwise discarded material leaving the process, separated by material and treatment destination.

  • Selected flow: Select material- and treatment-specific waste flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured dispatch mass or reconciled container mass by waste stream
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg accepted prepared material and parts issued to production
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_receiving_waste_records
  • Sources:
  • Range: Provisional receiving-waste screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0
    • Upper: 10
    • Unit: kg/kg accepted prepared material and parts
    • Basis: per kg accepted prepared material and parts issued to production; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Elementary flows

Process: Resistive-element formation (resistive_element_formation)

Inputs

Product flows
Prepared resistive-element materials (prepared_resistive_element_materials)

Record the prepared ceramic or other base, resistive film or paste constituents, composition compound, resistance wire, foil, or metal strip used by the declared route.

  • Selected flow: Select technology-specific prepared material product flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured issue mass by material and production lot
  • Value mode: Foreground record (foreground_record)
  • Specificity: Technology-specific (technology_specific)
  • Normalization basis: per kg accepted formed resistive elements
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_element_material_records
  • Sources: vishay-fixed-resistor-basics-2008
  • Range: Provisional element-material screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0.1
    • Upper: 20
    • Unit: kg/kg accepted formed resistive elements
    • Basis: per kg accepted formed resistive elements; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Formation-process electricity (element_formation_electricity)

Record metered electricity for route-applicable deposition, printing, pressing, curing, winding, etching, cutting, or laser and mechanical trimming operations.

  • Selected flow: Select geography- and voltage-specific electricity supply flow
  • Flow property / unit: Energy / kWh
  • Amount rule: submetered consumption, or documented allocation from a calibrated shared meter using machine operating time and rated or measured load
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg accepted formed resistive elements
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_element_utility_records
  • Sources: vishay-fixed-resistor-basics-2008
  • Range: Provisional formation-electricity screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0.01
    • Upper: 1000
    • Unit: kWh/kg accepted formed resistive elements
    • Basis: per kg accepted formed resistive elements; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Waste flows

Outputs

Product flows
Accepted formed resistive elements (accepted_formed_resistive_elements)

Record the measured mass of accepted formed elements transferred to termination and assembly after route-applicable trimming or intermediate inspection.

  • Selected flow: Select the technology-specific formed resistor-element intermediate product flow
  • Flow property / unit: Mass / kg
  • Amount rule: measured accepted transfer mass
  • Value mode: Foreground record (foreground_record)
  • Specificity: Technology-specific (technology_specific)
  • Normalization basis: process reference
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_element_output_records
  • Sources:
  • Range: Process quantitative-reference identity
    • Range role: Allowed range (allowed_range)
    • Lower: 1
    • Upper: 1
    • Unit: kg
    • Basis: per 1 kg accepted formed resistive elements used as the process quantitative reference
    • Basis kind: Process output (process_output)
    • Evidence kind: Method formula (method_formula)
    • Sources: eu-pef-2021-2279
Waste flows
Element-formation scrap and residues (element_formation_scrap_and_residues)

Record trimmings, spent paste or solution, rejected elements, sludge, and other residues by material composition and treatment destination. Internal return to the same process is tracked as rework, not external waste.

  • Selected flow: Select material- and treatment-specific waste flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured waste shipment or container mass reconciled to lot-level scrap records
  • Value mode: Foreground record (foreground_record)
  • Specificity: Technology-specific (technology_specific)
  • Normalization basis: per kg accepted formed resistive elements
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_element_waste_records
  • Sources:
  • Range: Provisional element-waste screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0
    • Upper: 10
    • Unit: kg/kg accepted formed resistive elements
    • Basis: per kg accepted formed resistive elements; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Elementary flows
Direct releases from element formation (element_formation_direct_releases)

Record measured or permit-calculated direct releases to air or water from route-applicable coating, printing, etching, cleaning, drying, curing, cutting, and trimming operations; do not substitute purchased chemical mass for an emitted amount.

  • Selected flow: Select substance- and compartment-specific elementary flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured release or calculation from monitored concentration and treated exhaust or effluent volume
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg accepted formed resistive elements
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_element_release_records
  • Sources: eu-pef-2021-2279
  • Range: Provisional direct-release screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0
    • Upper: 10
    • Unit: kg/kg accepted formed resistive elements
    • Basis: per kg accepted formed resistive elements; replace with measured or permit-calculated records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)

Process: Termination and mechanical assembly (termination_and_mechanical_assembly)

Inputs

Product flows
Formed resistive elements (formed_elements_for_assembly)

Record accepted formed elements entering termination and assembly, preserving technology and lot identity.

  • Selected flow: Select the matching technology-specific formed resistor-element intermediate product flow
  • Flow property / unit: Mass / kg
  • Amount rule: measured transfer mass
  • Value mode: Foreground record (foreground_record)
  • Specificity: Technology-specific (technology_specific)
  • Normalization basis: per kg assembled resistors before final finishing and testing
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_input_records
  • Sources:
  • Range: Provisional formed-element input screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0.1
    • Upper: 20
    • Unit: kg/kg assembled resistors
    • Basis: per kg assembled resistors before final finishing and testing; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Termination, contact, and mechanical parts (termination_contact_and_mechanical_parts)

Record terminals, lead wires, end caps, metallization or plating chemicals, conductive joining materials, and body or housing parts. For variable resistors, additionally record contacts, wipers, tracks, adjustment mechanisms, shafts, and multi-turn parts when present.

  • Selected flow: Select part- and material-specific product flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured issue mass or count converted with documented product-specific part mass
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per kg assembled resistors before final finishing and testing
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_part_records
  • Sources: iec-60393-1-2008; vishay-fixed-resistor-basics-2008
Assembly electricity (assembly_electricity)

Record metered electricity for welding, brazing, soldering, pressing, fastening, plating, curing, and mechanical adjustment performed in this process.

  • Selected flow: Select geography- and voltage-specific electricity supply flow
  • Flow property / unit: Energy / kWh
  • Amount rule: submetered consumption, or documented allocation from a calibrated shared meter using machine operating time and rated or measured load
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg assembled resistors before final finishing and testing
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_utility_records
  • Sources:
  • Range: Provisional assembly-electricity screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0.01
    • Upper: 1000
    • Unit: kWh/kg assembled resistors
    • Basis: per kg assembled resistors before final finishing and testing; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Waste flows

Outputs

Product flows
Assembled resistors before final finishing and testing (assembled_resistors)

Record the measured mass of assembled fixed or variable resistors transferred to final finishing and testing.

  • Selected flow: Select the matching assembled-resistor intermediate product flow
  • Flow property / unit: Mass / kg
  • Amount rule: measured accepted transfer mass
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: process reference
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_output_records
  • Sources:
  • Range: Process quantitative-reference identity
    • Range role: Allowed range (allowed_range)
    • Lower: 1
    • Upper: 1
    • Unit: kg
    • Basis: per 1 kg assembled resistors used as the process quantitative reference
    • Basis kind: Process output (process_output)
    • Evidence kind: Method formula (method_formula)
    • Sources: eu-pef-2021-2279
Waste flows
Assembly scrap and rejected parts (assembly_scrap_and_rejected_parts)

Record rejected elements, termination and lead scrap, contact and housing rejects, joining residues, and plating waste by material and treatment destination.

  • Selected flow: Select material- and treatment-specific waste flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured waste mass reconciled to production rejects and external dispatch records
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg assembled resistors before final finishing and testing
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_assembly_waste_records
  • Sources:
  • Range: Provisional assembly-waste screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0
    • Upper: 10
    • Unit: kg/kg assembled resistors
    • Basis: per kg assembled resistors before final finishing and testing; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Elementary flows

Process: Finishing, electrical testing, marking, and pack-out (finishing_testing_and_packout)

Inputs

Product flows
Assembled resistors for finishing (assembled_resistors_for_finishing)

Record assembled fixed or variable resistors entering route-applicable coating, encapsulation, curing, plating, marking, electrical testing, and pack-out.

  • Selected flow: Select the matching assembled-resistor intermediate product flow
  • Flow property / unit: Mass / kg
  • Amount rule: measured transfer mass
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per kg accepted finished electrical resistors
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finishing_input_records
  • Sources:
  • Range: Provisional assembled-product input screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0.1
    • Upper: 20
    • Unit: kg/kg accepted finished electrical resistors
    • Basis: per kg accepted finished electrical resistors; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Finishing, marking, and packaging materials (finishing_marking_and_packaging_materials)

Record route-applicable coatings, encapsulants, lacquers, marking media, cleaning chemicals, carriers, reels, trays, bags, cartons, and other packaging separately from net product mass.

  • Selected flow: Select material-specific product flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured issue or purchase mass corrected for documented stock change and returns
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: per kg accepted finished electrical resistors
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finishing_material_records
  • Sources: vishay-fixed-resistor-basics-2008
  • Range: Provisional finishing-material screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0
    • Upper: 20
    • Unit: kg/kg accepted finished electrical resistors
    • Basis: per kg accepted finished electrical resistors; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Finishing and test electricity (finishing_and_test_electricity)

Record metered electricity for coating or encapsulation, curing, marking, electrical screening, inspection, handling, and packaging equipment.

  • Selected flow: Select geography- and voltage-specific electricity supply flow
  • Flow property / unit: Energy / kWh
  • Amount rule: submetered consumption, or documented allocation from a calibrated shared meter using machine operating time and rated or measured load
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg accepted finished electrical resistors
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finishing_utility_records
  • Sources:
  • Range: Provisional finishing-and-test electricity screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0.01
    • Upper: 1000
    • Unit: kWh/kg accepted finished electrical resistors
    • Basis: per kg accepted finished electrical resistors; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Waste flows

Outputs

Product flows
Accepted finished electrical resistors (accepted_finished_electrical_resistors)

Record accepted output after electrical testing, inspection, marking, and release. Normalize the complete foreground inventory to 1 kg net mass of this output.

  • Selected flow: Electrical resistors (except heating resistors) 9bee079d-ab55-44db-b1a4-72d61a856d61
  • Flow property / unit: Mass / kg
  • Amount rule: measured net mass of accepted finished product; normalize the reported dataset to 1 kg
  • Value mode: Foreground record (foreground_record)
  • Specificity: Product-specific (product_specific)
  • Normalization basis: 1 kg accepted finished electrical resistors
  • Basis kind: Reference flow (reference_flow)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_final_product_and_qc_records
  • Sources: iec-60115-1-2020; iec-60393-1-2008
  • Range: Reference-flow identity
    • Range role: Allowed range (allowed_range)
    • Lower: 1
    • Upper: 1
    • Unit: kg
    • Basis: per 1 kg accepted finished electrical resistors used as the reference flow
    • Basis kind: Reference flow (reference_flow)
    • Evidence kind: Method formula (method_formula)
    • Sources: eu-pef-2021-2279
Waste flows
Off-specification product and finishing waste (off_specification_product_and_finishing_waste)

Record off-specification units not internally reworked, coating and encapsulation residues, spent cleaning materials, marking waste, and packaging scrap by material and treatment destination.

  • Selected flow: Select material- and treatment-specific waste flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured rejected or dispatched waste mass after subtracting documented internal rework
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg accepted finished electrical resistors
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finishing_waste_records
  • Sources:
  • Range: Provisional finishing-waste screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0
    • Upper: 10
    • Unit: kg/kg accepted finished electrical resistors
    • Basis: per kg accepted finished electrical resistors; replace with collected records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)
Elementary flows
Direct releases from finishing (finishing_direct_releases)

Record measured or permit-calculated air and water releases from coating, encapsulation, curing, cleaning, marking, and other included finishing operations.

  • Selected flow: Select substance- and compartment-specific elementary flows
  • Flow property / unit: Mass / kg
  • Amount rule: measured release or calculation from monitored concentration and treated exhaust or effluent volume
  • Value mode: Foreground record (foreground_record)
  • Specificity: Site-specific (site_specific)
  • Normalization basis: per kg accepted finished electrical resistors
  • Basis kind: Process output (process_output)
  • Evidence kind: Collected record (collected_record)
  • Collection protocol: cp_finishing_release_records
  • Sources: eu-pef-2021-2279
  • Range: Provisional finishing-release screening estimate
    • Range role: Default estimate (default_estimate)
    • Lower: 0
    • Upper: 10
    • Unit: kg/kg accepted finished electrical resistors
    • Basis: per kg accepted finished electrical resistors; replace with measured or permit-calculated records
    • Basis kind: Process output (process_output)
    • Evidence kind: Reasoned estimate (reasoned_estimate)

7. Allocation and Co-product Handling

rule_idApplies toRulesource_ids
allocation_avoid_by_subdivisionindependently measurable products, lines, or batchesAvoid allocation by subdividing product families, production lines, batches, and process records whenever inputs and outputs can be measured separately.eu-pef-2021-2279
allocation_internal_reworkinternal rework and recirculationKeep rework inside the process where it is reused, record its mass, and count only additional inputs, utilities, direct releases, and final losses caused by rework; do not treat the recirculated mass as a new external input or saleable co-product.eu-pef-2021-2279
allocation_shared_utilitiesshared meters and common servicesAllocate shared electricity, fuel, compressed air, water, and common treatment first by measured process consumption; when measurement is unavailable, use a documented causal physical driver such as machine operating time multiplied by measured or rated load.eu-pef-2021-2279
allocation_co_productsjointly produced saleable productsAfter subdivision has been exhausted, use a documented physical relationship that reflects the causal production relationship; if no defensible physical relationship can be established, use economic allocation based on a representative price period and report the sensitivity.eu-pef-2021-2279
allocation_scraprecoverable scrap and residuesRecord treatment up to the foreground gate and disclose the applied recycling or substitution convention. Do not assign an avoided-product credit or zero burden without the governing study method and explicit evidence.eu-pef-2021-2279

8. Foreground Data Collection, Calculation, and Quality Rules

Data Collection Protocols

protocol_idprocess_idflow_rolerecord_typeraw_fieldscollection_methodunitfrequencytemporal_coveragesite_scopeaggregation_rulequality_evidence
cp_receiving_material_recordsmaterial_receiving_and_preparationPurchased constituent materials and partspurchase, receiving, issue, and inventory recordsmaterial or part id; supplier; lot; mass or count; concentration when applicable; receipt and issue dates; opening and closing stock; returnscalibrated weighing or count converted with documented part mass, reconciled to inventorykgper receipt and issuerepresentative reporting period, normally at least twelve consecutive months unless a shorter campaign is justifieddeclared manufacturing sitesum by material and lot; add opening stock and subtract closing stock and returns; normalize to prepared outputscale calibration; supplier specification; inventory reconciliation
cp_prepared_material_outputmaterial_receiving_and_preparationPrepared materials and parts issued to productionpreparation and issue recordmaterial id; lot; issued mass; prepared stock change; destination processcalibrated weighing and inventory issue recordkgper lot or issuesame period as represented productiondeclared manufacturing sitesum accepted issues and stock change by routescale calibration; signed issue record
cp_receiving_waste_recordsmaterial_receiving_and_preparationRejected incoming material and preparation wastewaste log and dispatch recordwaste id; composition; mass; date; destination; internal rework statuscalibrated scale or reconciled container masskgper waste movementsame period as represented productiondeclared manufacturing sitesum external waste by stream; exclude documented internal reworkwaste manifest; scale calibration
cp_element_material_recordsresistive_element_formationPrepared resistive-element materialsbatch issue recordmaterial id; lot; issue mass; returned mass; route; batch idcalibrated weighing and batch reconciliationkgper batchsame period as represented productionelement-formation area at declared sitenet issued mass by material and routescale calibration; batch record
cp_element_utility_recordsresistive_element_formationFormation-process electricitysubmeter or equipment energy recordmeter id; start and end reading; machine id; operating time; measured or rated load; batch idcalibrated submeter preferred; otherwise documented causal allocationkWhcontinuous, shift, or batchsame period as represented productionelement-formation area at declared sitesubtract readings and allocate only documented shared consumptionmeter calibration; allocation worksheet
cp_element_output_recordsresistive_element_formationAccepted formed resistive elementstransfer and inspection recordlot; technology; gross mass; accepted mass; rejected mass; datecalibrated weighing at transferkgper lotsame period as represented productionelement-formation area at declared sitesum accepted transfer mass by technologyscale calibration; inspection release
cp_element_waste_recordsresistive_element_formationElement-formation scrap and residuesscrap log, waste manifest, and inventory reconciliationwaste id; composition; mass; date; destination; rework quantitycalibrated weighing or container reconciliationkgper batch and dispatchsame period as represented productionelement-formation area at declared sitesum external waste by stream after removing documented reworkwaste manifest; mass-balance reconciliation
cp_element_release_recordsresistive_element_formationDirect releases from element formationmonitoring and permit recordsubstance; compartment; concentration; exhaust or effluent volume; time; treatment statusdirect monitoring or concentration-volume calculationkgper monitoring event with reporting-period coveragesame period as represented productioncontrolled emission points at declared sitecalculate and sum releases by substance and compartmentlaboratory report; instrument calibration; calculation sheet
cp_assembly_input_recordstermination_and_mechanical_assemblyFormed resistive elementstransfer recordlot; technology; transferred mass; datecalibrated weighingkgper lotsame period as represented productionassembly area at declared sitesum transferred mass by represented product familyscale calibration; transfer record
cp_assembly_part_recordstermination_and_mechanical_assemblyTermination, contact, and mechanical partsissue and bill-of-material recordspart or material id; lot; mass or count; product-specific part mass; returned quantity; product familycalibrated weighing or count-to-mass conversion with documented samplekgper lot or batchsame period as represented productionassembly area at declared sitenet issue by part and product familyscale calibration; bill of materials; sampling record
cp_assembly_utility_recordstermination_and_mechanical_assemblyAssembly electricitysubmeter or equipment energy recordmeter id; readings; machine id; operating time; load; batch idcalibrated submeter preferred; otherwise documented causal allocationkWhcontinuous, shift, or batchsame period as represented productionassembly area at declared sitesubtract readings and allocate only documented shared consumptionmeter calibration; allocation worksheet
cp_assembly_output_recordstermination_and_mechanical_assemblyAssembled resistors before final finishing and testingtransfer and inspection recordlot; product family; gross mass; accepted mass; rejected mass; datecalibrated weighing at transferkgper lotsame period as represented productionassembly area at declared sitesum accepted transfer mass by product familyscale calibration; inspection release
cp_assembly_waste_recordstermination_and_mechanical_assemblyAssembly scrap and rejected partsscrap log and waste manifestwaste id; composition; mass; date; destination; rework quantitycalibrated weighing or container reconciliationkgper batch and dispatchsame period as represented productionassembly area at declared sitesum external waste by stream after removing documented reworkwaste manifest; mass-balance reconciliation
cp_finishing_input_recordsfinishing_testing_and_packoutAssembled resistors for finishingtransfer recordlot; product family; transferred mass; datecalibrated weighingkgper lotsame period as represented productionfinishing area at declared sitesum transferred mass by product familyscale calibration; transfer record
cp_finishing_material_recordsfinishing_testing_and_packoutFinishing, marking, and packaging materialsissue, purchase, and stock recordmaterial id; lot; issue mass; purchase mass; opening and closing stock; returns; packaging typecalibrated weighing and inventory reconciliationkgper issue with period reconciliationsame period as represented productionfinishing and pack-out areas at declared sitenet consumption by material; packaging reported separately from product massscale calibration; inventory reconciliation
cp_finishing_utility_recordsfinishing_testing_and_packoutFinishing and test electricitysubmeter or equipment energy recordmeter id; readings; machine id; operating time; load; batch idcalibrated submeter preferred; otherwise documented causal allocationkWhcontinuous, shift, or batchsame period as represented productionfinishing, test, and pack-out areas at declared sitesubtract readings and allocate only documented shared consumptionmeter calibration; allocation worksheet
cp_final_product_and_qc_recordsfinishing_testing_and_packoutAccepted finished electrical resistorsproduction, weighing, and quality release recordproduct code; lot; fixed or variable family; technology; form; resistance or range; tolerance; rated dissipation; stability descriptor; net accepted mass; packaging mass; test status; datecalibrated net-mass weighing linked to electrical test and release recordskgper released lotsame period as represented productiondeclared manufacturing site and plant gatesum accepted net product mass; normalize all included flows to 1 kgscale and test-equipment calibration; lot release; product specification
cp_finishing_waste_recordsfinishing_testing_and_packoutOff-specification product and finishing wastereject, rework, and waste dispatch recordproduct or waste id; composition; mass; rework quantity; date; destinationcalibrated weighing and reject reconciliationkgper lot and dispatchsame period as represented productionfinishing and pack-out areas at declared sitesum external waste after subtracting documented internal reworkreject log; waste manifest; mass balance
cp_finishing_release_recordsfinishing_testing_and_packoutDirect releases from finishingmonitoring and permit recordsubstance; compartment; concentration; exhaust or effluent volume; time; treatment statusdirect monitoring or concentration-volume calculationkgper monitoring event with reporting-period coveragesame period as represented productioncontrolled emission points at declared sitecalculate and sum releases by substance and compartmentlaboratory report; instrument calibration; calculation sheet

Calculation Rules

rule_idApplies toFormula or ruleInputsOutputsource_ids
normalize_to_reference_massall included inventory rowsnormalized amount = reporting-period amount / accepted finished net product mass × 1 kgaggregated protocol record; accepted net product mass from cp_final_product_and_qc_recordsamount per 1 kg accepted finished electrical resistorseu-pef-2021-2279
convert_count_to_masspart or product records available as countsmass = item count × measured product-specific mean item mass; the mean is total calibrated sample mass divided by sample countcount record; sampled item count; calibrated sample masskg material, parts, or accepted product
calculate_direct_releaseconcentration-and-volume emission recordsreleased mass = monitored concentration × treated exhaust or effluent volume, with explicit compatible-unit conversion and treatment statusconcentration; flow or volume; monitoring period; unit conversionkg substance released to the declared compartmenteu-pef-2021-2279
reconcile_process_masseach process and reporting periodmass discrepancy = external material inputs + opening work-in-progress − accepted transfers − external wastes − closing work-in-progress; internal rework is reported but cancels from the external balancematerial, output, waste, stock, and rework protocolsdocumented mass-balance discrepancy and investigation statuseu-pef-2021-2279
allocate_shared_energyshared electricity or fuel meterprocess energy = shared-meter consumption × documented causal driver for the process / sum of the same driver for all usersmeter readings; operating time; measured or rated load, or another justified physical driverkWh or MJ assigned to the included processeu-pef-2021-2279

Data Quality Requirements

requirement_idApplies toRequirementEvidence
dq_product_identityreference product and production mixPreserve product code and lot linkage to fixed or variable family, technology, form, resistance or range, tolerance, rated dissipation, stability descriptor, termination, housing or package, and conformity result.product specification; bill of materials; route sheet; lot release record
dq_technological_representativenessforeground and upstream dataForeground records must represent the declared resistor technologies and forms; upstream datasets must match material grade and production technology where material. Document any proxy.technology coverage matrix; supplier data; proxy justification
dq_geographical_representativenessutilities, upstream inputs, and treatmentUse datasets and mixes representative of the declared manufacturing site and supplier or treatment geography; document mismatches.site address; supplier origin; utility contract; dataset metadata
dq_time_representativenessreporting-period dataPrefer a continuous representative period covering seasonal and production-mix variation, normally at least twelve consecutive months; justify a shorter campaign and disclose data age.reporting calendar; production schedule; dated records
dq_measurement_and_precisionmeasured mass, energy, and releasesIdentify measurement equipment, calibration status, resolution, sampling method, and calculation steps sufficient to reproduce material amounts and direct releases.calibration certificates; sampling plan; calculation workbook
dq_completeness_and_balanceall included processesReconcile material inputs, accepted transfers, product, work-in-progress changes, internal rework, wastes, and direct releases; investigate material discrepancies and disclose unresolved gaps without applying an undocumented cut-off.process mass balances; exception log; completeness review
dq_primary_and_secondary_dataforeground collection and upstream linksUse site- or company-specific primary data for directly controlled foreground processes and document the source, representativeness, and quality of each secondary dataset.meter and production records; supplier records; secondary-dataset register; data-quality rating
dq_restricted_substancesproducts placed on regulated marketsWhen applicable, maintain current material declarations, exemption status, and risk-based analytical evidence for restricted substances; screening and confirmatory testing must use the applicable current IEC 62321 parts and jurisdictional requirements.supplier declarations; bill of materials; exemption register; accredited laboratory report

9. Validation Rules

rule_idApplies toRulesource_ids
validate_category_identityproduct category and reference flowThe represented output must be a finished fixed or variable electrical resistor within CPC 47120 and must not be a heating resistor, generic resistive material, unassembled element, broader electronic-component mix, or resistor-containing assembly with another principal function.unsd-cpc-3-0-structure; iec-60115-1-2020; iec-60393-1-2008
validate_reference_flowfunctional unit and quantitative referenceThe reference output must use product flow 9bee079d-ab55-44db-b1a4-72d61a856d61, Mass 93a60a56-a3c8-11da-a746-0800200b9a66, Units of mass 93a60a57-a4c8-11da-a746-0800200c9a66, and kg, normalized to exactly 1 kg net accepted finished product.
validate_required_qualifiersforeground package metadataEvery required qualifier in section 3 must be present and consistent with product, bill-of-material, route, test, and release records.iec-60115-1-2020; iec-60393-1-2008
validate_process_routeprocess map and inventoryEach included route step and conditional variable-resistor assembly must match the declared product family and technology; absent operations must not receive invented flows, and outsourced operations must be linked and disclosed.vishay-fixed-resistor-basics-2008
validate_collection_linkscollected or calculated inventory rowsEvery collected or calculated amount must link to a listed collection protocol and retain the specified raw fields, period, site scope, aggregation, and quality evidence.eu-pef-2021-2279
validate_mass_balanceeach process and full foreground systemMaterial inputs, accepted transfers, stock changes, internal rework, product, wastes, and direct releases must be reconciled; any unresolved discrepancy must be quantified and makes validation inconclusive.eu-pef-2021-2279
validate_allocationshared processes, co-products, and recoverable scrapApplied subdivision, causal driver, allocation basis, price period, recycling convention, and sensitivity must comply with section 7 and be disclosed wherever relevant.eu-pef-2021-2279
validate_completenessincluded inventoryNo material, energy, water, direct-release, waste, or treatment flow may be omitted solely because it is small; all exclusions, data gaps, and proxies must be disclosed and justified.eu-pef-2021-2279
validate_restricted_substance_evidenceregulated-market conformity disclosureIf restricted-substance conformity is claimed, the applicable jurisdiction, current exemptions, supplier evidence, test method, laboratory, sample, date, and result must be documented; a screening result alone must not be presented as universal legal compliance.eu-rohs-2011-65-eu; iec-62321-series

10. Published Dataset Profile

FieldValue
dataset_roleforeground_product_system; unit_process_or_aggregated_process_dataset
downstream_useforeground_data_package; process; lifecyclemodel; comparative or non-comparative LCA subject to matching scope
allowed_useProduction of finished electrical resistors except heating resistors when product family, technology, form, performance qualifiers, geography, period, production mix, and plant gate match the represented data
excluded_useHeating resistors; raw or unassembled resistive materials; generic electronic components; downstream distribution, installation, use, maintenance, or end-of-life modelling without additional datasets
required_metadatacanonical PCR id; CPC 3.0 code; reference flow UUIDs; required qualifiers; plant and geography; reporting period; production mix; process coverage; outsourced steps; upstream datasets; allocation and recycling conventions; conformity basis
required_quality_disclosureprotocol coverage; primary-data share; technological, geographical, and time representativeness; measurement and sampling evidence; mass-balance results; proxies; gaps; exclusions; allocation sensitivity; restricted-substance evidence when claimed
update_triggerChange in product scope, resistor technology or form, plant or route, bill of materials, energy or treatment system, allocation convention, applicable regulation or standard, Tiangong identity, or data older than the declared representativeness period

11. Data Sources

Source idTypeReferenceUsed for
unsd-cpc-3-0-structureofficial_guidanceUnited Nations Statistics Division, Central Product Classification Version 3.0 structure, CPC 47120, 2023, https://unstats.un.org/unsd/classifications/Meetings/UNCEISC2023/8-3_Background3_CPC3_Structure.pdf, retrieved 2026-08-09official product-category identity and exclusion of heating resistors
iec-60115-1-2020standardIEC 60115-1:2020, Fixed resistors for use in electronic equipment — Part 1: Generic specification, https://webstore.iec.ch/en/publication/28476, retrieved 2026-08-09fixed-resistor scope, terminology, performance qualifiers, inspection, and test context
iec-60393-1-2008standardIEC 60393-1:2008, Potentiometers for use in electronic equipment — Part 1: Generic specification, https://webstore.iec.ch/en/publication/2017, retrieved 2026-08-09variable-resistor and potentiometer scope, forms, terminology, inspection, and test context
vishay-fixed-resistor-basics-2008handbookVishay, Basics of Linear Fixed Resistors, Technical Note TN0002, revision 23 October 2008, https://www.vishay.com/docs/28771/basics.pdf, retrieved 2026-08-09fixed-resistor technology families, materials, formation, termination, trimming, coating, marking, and test route evidence
eu-rohs-2011-65-eustandardDirective 2011/65/EU on restriction of hazardous substances in electrical and electronic equipment, current consolidated text, https://eur-lex.europa.eu/eli/dir/2011/65/2026-07-01/eng, retrieved 2026-08-09jurisdiction-dependent restricted-substance conformity and exemption evidence
iec-62321-seriesstandardIEC 62321 series, Determination of certain substances in electrotechnical products; current IEC 62321-3-1:2026 screening methods page, https://webstore.iec.ch/en/publication/66313, retrieved 2026-08-09risk-based restricted-substance screening and analytical-method disclosure
eu-pef-2021-2279official_guidanceEuropean Commission Recommendation (EU) 2021/2279 on the use of Environmental Footprint methods, consolidated text, https://eur-lex.europa.eu/legal-content/EN/TXT/HTML/?uri=CELEX:02021H2279-20211230, retrieved 2026-08-09foreground primary data, subdivision and allocation, no undocumented cut-off, calculation, representativeness, completeness, and data-quality rules

Raw downloads

These files are byte-identical to the canonical files for this revision in the repository.

Structured rule index

This index comes from verified structured.yaml and retains the canonical English rule text.

System boundary rules · 5
Rule IDApplies toRuleSource IDs
boundary_gate_to_gateforeground productionInclude constituent-material and part receiving and preparation, resistive-element formation, termination and mechanical assembly, route-applicable coating or encapsulation, electrical testing, marking, and pack-out through accepted product at the plant gate.vishay-fixed-resistor-basics-2008
boundary_route_declarationall represented product familiesDeclare whether the product is fixed or variable and identify the actual technology and form; include contact, wiper, adjustment-mechanism, shaft, housing, or multi-turn assembly only when present, and do not add absent route steps.iec-60115-1-2020, iec-60393-1-2008, vishay-fixed-resistor-basics-2008
boundary_upstream_linkspurchased products and servicesLink purchased substrates, cores, resistive materials, wires or foils, termination and contact materials, housings, coatings, encapsulants, process chemicals, packaging, energy carriers, water, and external treatment services to suitable upstream datasets; retain supplier-primary data where available.eu-pef-2021-2279
boundary_direct_releasessite-controlled operationsInclude measured or permitted direct air emissions, wastewater releases, and wastes caused by included processes, with the treatment or destination declared.eu-pef-2021-2279
boundary_exclusionsdownstream and capital activitiesExclude distribution beyond the plant gate, installation, use, maintenance, and end of life. Exclude capital goods only when the study method permits and disclose that exclusion; do not exclude material or energy flows merely because they are small.eu-pef-2021-2279
Allocation rules · 5
Rule IDApplies toRuleSource IDs
allocation_avoid_by_subdivisionindependently measurable products, lines, or batchesAvoid allocation by subdividing product families, production lines, batches, and process records whenever inputs and outputs can be measured separately.eu-pef-2021-2279
allocation_internal_reworkinternal rework and recirculationKeep rework inside the process where it is reused, record its mass, and count only additional inputs, utilities, direct releases, and final losses caused by rework; do not treat the recirculated mass as a new external input or saleable co-product.eu-pef-2021-2279
allocation_shared_utilitiesshared meters and common servicesAllocate shared electricity, fuel, compressed air, water, and common treatment first by measured process consumption; when measurement is unavailable, use a documented causal physical driver such as machine operating time multiplied by measured or rated load.eu-pef-2021-2279
allocation_co_productsjointly produced saleable productsAfter subdivision has been exhausted, use a documented physical relationship that reflects the causal production relationship; if no defensible physical relationship can be established, use economic allocation based on a representative price period and report the sensitivity.eu-pef-2021-2279
allocation_scraprecoverable scrap and residuesRecord treatment up to the foreground gate and disclose the applied recycling or substitution convention. Do not assign an avoided-product credit or zero burden without the governing study method and explicit evidence.eu-pef-2021-2279
Validation rules · 9
Rule IDApplies toRuleSource IDs
validate_category_identityproduct category and reference flowThe represented output must be a finished fixed or variable electrical resistor within CPC 47120 and must not be a heating resistor, generic resistive material, unassembled element, broader electronic-component mix, or resistor-containing assembly with another principal function.unsd-cpc-3-0-structure, iec-60115-1-2020, iec-60393-1-2008
validate_reference_flowfunctional unit and quantitative referenceThe reference output must use product flow 9bee079d-ab55-44db-b1a4-72d61a856d61, Mass 93a60a56-a3c8-11da-a746-0800200b9a66, Units of mass 93a60a57-a4c8-11da-a746-0800200c9a66, and kg, normalized to exactly 1 kg net accepted finished product.
validate_required_qualifiersforeground package metadataEvery required qualifier in section 3 must be present and consistent with product, bill-of-material, route, test, and release records.iec-60115-1-2020, iec-60393-1-2008
validate_process_routeprocess map and inventoryEach included route step and conditional variable-resistor assembly must match the declared product family and technology; absent operations must not receive invented flows, and outsourced operations must be linked and disclosed.vishay-fixed-resistor-basics-2008
validate_collection_linkscollected or calculated inventory rowsEvery collected or calculated amount must link to a listed collection protocol and retain the specified raw fields, period, site scope, aggregation, and quality evidence.eu-pef-2021-2279
validate_mass_balanceeach process and full foreground systemMaterial inputs, accepted transfers, stock changes, internal rework, product, wastes, and direct releases must be reconciled; any unresolved discrepancy must be quantified and makes validation inconclusive.eu-pef-2021-2279
validate_allocationshared processes, co-products, and recoverable scrapApplied subdivision, causal driver, allocation basis, price period, recycling convention, and sensitivity must comply with section 7 and be disclosed wherever relevant.eu-pef-2021-2279
validate_completenessincluded inventoryNo material, energy, water, direct-release, waste, or treatment flow may be omitted solely because it is small; all exclusions, data gaps, and proxies must be disclosed and justified.eu-pef-2021-2279
validate_restricted_substance_evidenceregulated-market conformity disclosureIf restricted-substance conformity is claimed, the applicable jurisdiction, current exemptions, supplier evidence, test method, laboratory, sample, date, and result must be documented; a screening result alone must not be presented as universal legal compliance.eu-rohs-2011-65-eu, iec-62321-series
Processes and inputs/outputs · 4
Process IDProcess nameInput flowsOutput flows
material_receiving_and_preparationMaterial receiving and preparation12
resistive_element_formationResistive-element formation23
termination_and_mechanical_assemblyTermination and mechanical assembly32
finishing_testing_and_packoutFinishing, electrical testing, marking, and pack-out33

Complete field inspector

Loads this record’s complete manifest and structured projection on demand; values are never truncated. Requires JavaScript.

On this page

1. Scope and Applicability2. Product Category Identity3. Reference Flow4. Measurement and Unit Rules5. System BoundaryBoundary Abstraction6. Process Inventory StructureProcess MapProcess: Material receiving and preparation (material_receiving_and_preparation)InputsProduct flowsPurchased constituent materials and parts (purchased_constituent_materials_and_parts)Waste flowsOutputsProduct flowsPrepared materials and parts issued to production (prepared_materials_and_parts)Waste flowsRejected incoming material and preparation waste (receiving_and_preparation_waste)Elementary flowsProcess: Resistive-element formation (resistive_element_formation)InputsProduct flowsPrepared resistive-element materials (prepared_resistive_element_materials)Formation-process electricity (element_formation_electricity)Waste flowsOutputsProduct flowsAccepted formed resistive elements (accepted_formed_resistive_elements)Waste flowsElement-formation scrap and residues (element_formation_scrap_and_residues)Elementary flowsDirect releases from element formation (element_formation_direct_releases)Process: Termination and mechanical assembly (termination_and_mechanical_assembly)InputsProduct flowsFormed resistive elements (formed_elements_for_assembly)Termination, contact, and mechanical parts (termination_contact_and_mechanical_parts)Assembly electricity (assembly_electricity)Waste flowsOutputsProduct flowsAssembled resistors before final finishing and testing (assembled_resistors)Waste flowsAssembly scrap and rejected parts (assembly_scrap_and_rejected_parts)Elementary flowsProcess: Finishing, electrical testing, marking, and pack-out (finishing_testing_and_packout)InputsProduct flowsAssembled resistors for finishing (assembled_resistors_for_finishing)Finishing, marking, and packaging materials (finishing_marking_and_packaging_materials)Finishing and test electricity (finishing_and_test_electricity)Waste flowsOutputsProduct flowsAccepted finished electrical resistors (accepted_finished_electrical_resistors)Waste flowsOff-specification product and finishing waste (off_specification_product_and_finishing_waste)Elementary flowsDirect releases from finishing (finishing_direct_releases)7. Allocation and Co-product Handling8. Foreground Data Collection, Calculation, and Quality RulesData Collection ProtocolsCalculation RulesData Quality Requirements9. Validation Rules10. Published Dataset Profile11. Data Sources